Mohsen, O; Petre, C and Mohamed, Y (2023) Machine-learning approach to predict total fabrication duration of industrial pipe spools. Journal of Construction Engineering and Management, 149(2): 04022172, ISSN 0733-9364
Abstract
In industrial modular construction, components fabricated in the shop are assembled into modules before being transported to construction sites. This approach offers improved construction efficiency, higher quality products, and the opportunity to work in a controlled environment that offers more predictable schedules. A distinct category of modularized construction is that of piping structures where prefabricated segments of pipes, called pipe spools, are arranged and attached to a steel structure to speed up on-site assembly. Determining when a particular pipe spool is ready for delivery to the site is affected by many factors, including material availability, workforce performance and availability, shop loading conditions, and shop capacity. These factors combine to produce a high degree of uncertainty when estimating the fabrication duration. This paper investigates the improvement of delivery time prediction of pipe spools that are fabricated in a manufacturing facility. The study's main contribution is to propose a data-driven machine-learning model that accurately predicts the total fabrication duration in a pipe spool fabrication facility. The developed model is expected to assist production managers to plan for the appropriate workforce and material delivery requirements. The proposed approach utilizes a combination of product composition and real-time loading status of the shop to develop and examine several tree-based machine-learning models. The approach was evaluated using records of 6,989 pipe spools. The overall prediction performance was improved by a reduction of 35% in the mean absolute percentage error compared to original heuristic estimates. The results also show a strong positive correlation of 0.8 between the actual and predicted values.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | fabrication duration; industrial construction; machine learning; modular construction; offsite construction; pipe spool; time prediction |
| Index terms: | heuristic, machine learning, efficiency, modular construction, industrial construction, module, time prediction, fabrication, steel structure, delivery time, estimating, estimate, manager, loading, construction site, duration |
| Subjects: | construction operations, work location, time analysis, building construction, specialized materials and systems, practitioner, risk assessment, project controls, manufacturing engineering, performance management, operations research, architectural elements, financial and cost management, artificial intelligence |
| Topics: | Engineering Principles, Design Practice, Risk Management, Digital Applications, Construction Materials, Roles and Professions, Time Control, Quality Management, Site Management, Cost Management, Construction Technology |
| Descriptive scope: | 2 PC |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here