4D BIM-enabled look-ahead scheduling for early warning of off-site supply chain disruptions

Zeng, N; Liu, Y and König, M (2023) 4D BIM-enabled look-ahead scheduling for early warning of off-site supply chain disruptions. Journal of Construction Engineering and Management, 149(1): 04022154, ISSN 0733-9364

Abstract

A common problem in construction is that disruptions emerging in the off-site supply chain adversely influence on-site activities. Off-site disruptions may cause substantial construction delays if they are not identified in time. Based on the production theory and four-dimensional (4D) building information modeling (BIM) applications in construction, this paper proposes a novel framework that assists in developing look-ahead supply schedules to identify potential construction delays caused by off-site disruptions. The framework adopts an extended customer order decoupling point (CODP) typology to define off-site process patterns, reflecting the production features and supply characteristics. The early warning signs of potential construction delays are captured by checking the integrated on- and off-site process and further visualized in a BIM-enabled environment. A case study is carried out to verify the feasibility of the framework and identify practical implications. Guided by the framework, construction project teams and suppliers can identify the early warning signs of potential delays, aided by specific location and duration instructions from the 4D BIM. This framework will help prevent off-site disruptions and offer adaptability for construction and logistics scheduling and planning.

Item Type: Article
Uncontrolled Keywords: building information modeling; construction supply chain; customer order decoupling point; early warning; four-dimensional BIM
Index terms: construction supply chain, duration, case study, construction project team, building information modelling, site process, look-ahead scheduling, adaptability, construction delay, scheduling, early warning, decoupling
Subjects: construction logistics, user focus, data collection methods, project delivery, operations management, operations research, financial risk, information systems, systems engineering, project controls
Topics: Time Control, Site Management, Design Practice, Digital Applications, Supply Chain Management, Cost Management, Research Practice, Project Management, Engineering Principles
Descriptive scope: 3 PCE

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here