Optimum finance-based scheduling

Akin, F D; Damci, A and Arditi, D (2024) Optimum finance-based scheduling. Journal of Construction Engineering and Management, 150(9): 04024104, ISSN 0733-9364

Abstract

Even though advanced heuristic and metaheuristic models have been developed for minimizing financing cost by using total float to adjust the start times of activities, these models overlook the fact that the attempt to minimize financing cost may result in more than one work schedule with minimum financing cost. It is therefore not surprising that no research has been conducted to select the best financing schedule out of the multiple optimal work schedules. It is well known that total float must be used sparingly to avoid the creation of too many critical and near-critical activities that may cause delays in the project duration. Indeed, the loss of schedule flexibility caused by the use of total float comes at a cost. It is argued in this paper that the cost of float consumption should be a vital part of models designed to minimize financing cost. The research presented in this paper attempts to fill this gap. A model is proposed in this study that not only minimizes financing cost but also demonstrates the negative impact of not considering the cost of float consumption in reaching the optimal solution, an area of research that is mostly overlooked in the finance-based scheduling literature. This research contributes to the body of knowledge by demonstrating that there may be more than one work schedule with minimum financing cost, and that the cost of float consumption must be considered to find the most optimal solution.

Item Type: Article
Uncontrolled Keywords: finance-based scheduling; financing cost; optimal financing models; total float
Index terms: financing, scheduling, consumption, duration, heuristic, body of knowledge
Subjects: operations research, project controls, economic analysis, consumer economics, risk assessment, knowledge management
Topics: Time Control, Risk Management, Business Strategy, Information Management, Stakeholder Management
Descriptive scope: 2 PC

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here