Wang, R D; Zayed, T; Eltoukhy, A E E and Wu, H (2024) Integrated planning approach for optimizing tower crane and truck locations in modular integrated construction. Journal of Construction Engineering and Management, 150(9): 04024121, ISSN 0733-9364
Abstract
Tower crane layout planning (TCLP) is key to ensure the safety and productivity of construction projects. Previous studies on TCLP mainly focused on the typical in situ construction method, however, overlooking modular integrated construction (MiC). This study aims to develop an integrated planning approach for optimizing the locations of tower cranes and trucks for MiC across the entire construction site. This approach consists of four objective components. First, identifying potential locations for cranes and trucks by adopting a gridding method and an intersection examination algorithm. Second, estimating the crane operation duration. Third, optimizing the crane and truck locations by developing an integer linear programming (ILP) model while considering various constraints, such as the demand fulfillment, the crane's lifting capacity, and the multiple truck parking areas. Lastly, optimizing the distance between cranes to avoid crane blocking on site. The proposed approach is validated via three high-rise residential MiC projects. The results achieve 19.4%-37.9% reductions in cranes' operation durations, as well as carbon emissions from the original plan. Compared with another existing TCLP method made from limited predefined layout plans, a 29.4% improvement is observed. Moreover, three aspects to extend the application of the approach are discussed: (1) the multiple tower crane layout scenario, (2) the impact of the number of truck points, and (3) the trade-offs between computing effectiveness and performance. The approach realizes the objective of TCLP decision-making for multi-crane multitruck MiC throughout the whole construction site. Construction practitioners can use this approach for decision-making which helps enhance the effectiveness of their tower crane layout designs.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | integer linear programming; modular integrated construction; tower crane layout planning; truck location |
| Index terms: | productivity, tower crane, linear programming, carbon emission, duration, in-situ, effectiveness, construction site, construction method, construction practitioner, estimating, decision-making, construction project, computing, lifting |
| Subjects: | computing systems, climate science, financial and cost management, work location, professional development, production management, performance management, maintenance engineering, algorithms, management, decision analysis, building construction, occupational health and safety management, project controls |
| Topics: | Risk Management, Sustainability, Cost Management, Business Strategy, Health and Safety, Project Management, Engineering Principles, Information Management, Time Control, Site Management, Digital Applications, Quality Management |
| Descriptive scope: | 3 PCA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here