Zarghami, S A (2024) No scheduling problem but rather a rescheduling problem: Measuring robustness of schedule network in construction projects. Journal of Construction Engineering and Management, 150(2): 04023157, ISSN 0733-9364
Abstract
The available slack-based methods for measuring the robustness of schedule networks do not pay sufficient attention to the structural characteristics of such networks nor do they provide a comparison point for measuring the sensitivity to changes. This research fills these gaps by addressing a core research question: How can an integrative measure of schedule robustness be developed? To answer this question, this paper performs a centrality analysis to capture the structural characteristics of the schedule network. Further, it draws on the concept of perfect uniformity to establish a baseline for measuring the degree of schedule sensitivity to disruptions. Finally, it uses entropy theory to develop an integrative measure of schedule robustness by combining two classes of robustness measures: quality and solution robustness. An experimental analysis is undertaken to evaluate the statistical performance of the new measure. The validation results show a high inverse correlation between the proposed measure and a cost-based indicator of schedule performance; in turn, proving the better performance of the new measure compared to the two widely discussed and quoted slack-based measures of robustness. This can be ascribed to the ability of the new measure to simultaneously capture various attributes of a schedule network. The results of this research can assist decision makers in making informed decisions in the appraisal and monitoring phases of construction projects. This research provides the opportunity for future studies to extend the proposed method by incorporating resource-constrained and cost-related attributes of project activities into the formulation of schedule robustness.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | construction projects; disruptions; project schedule; schedule robustness; slack |
| Index terms: | appraisal, construction project, validation, slack, entropy, scheduling, schedule performance, future study, monitoring |
| Subjects: | factor and component analysis, production management, professional development, project controls, thermal systems, research design and methodology, control systems, operations research |
| Topics: | Site Management, Time Control, Sustainability, Project Management, Research Practice, Information Management |
| Descriptive scope: | 3 PCA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here