Fox, J V S (2014) Incentives and limits in letters of intent: Are they worth the paper they're written on? International Journal of Law in the Built Environment, 6(3), pp. 214-232. ISSN 1756-1450
Abstract
Purpose – The purpose of this paper is to review the extensive case law in England and Wales on contractually binding letters of intent. The research focused on discovering whether the limits commonly found in binding letters of intent were upheld by the courts and so were effective in practice. It also reviews whether these limits are, as presumed by drafters, sufficient to act as incentives to the parties to conclude the full contract. The paper uses case law to analyse and evaluate the legal and business efficacy of these limits and incentives. It considers the rationale for such limits and incentives before drawing its conclusions and making recommendations. Design/methodology/approach – The paper draws on cases in England and Wales to analyse the judicial interpretation of binding letters of intent. The author has adopted a black letter approach to this subject by focusing almost exclusively on primary sources. As there is no relevant legislation in England and Wales, the primary sources are case law. A limited literature review was adopted, as there is little commentary on this aspect of letters of intent and to ensure the paper’s originality. The paper also considers papers published by the Society for Construction Law. Findings – The paper demonstrates that even if the drafting of the letter of intent is clear, it is the conduct of the parties after a letter of intent which prevents the stated limits on work times or cost applying, and undermines these limits in their roles as incentives intended to persuade the parties to conclude the full contract for the project. The terms of the letter of intent are easily ousted and may not be strictly enforced by the courts when a dispute arises. Practical implications – The paper concludes with recommendations for ensuring the terms of the commonly used letters of intent provide more effective limits on the liability for the employer while giving the constructor the incentive to continue negotiating and concluding a formal contract for the works. The paper also recommends changes to the guidance to be given to users of standard form letters of intent to improve their efficacy as limited contracts. Originality/value – The analysis of the cases is instructive and the recommendations provide valuable pointers for those who draft, review or agree letters of intent. The issues that are dealt with relate to how the parties can be incentivised through clear drafting to execute a more comprehensive contract for the project.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | incentives; case law; construction law; letters of intent; limits on liability; contractually binding |
| Index terms: | methodology, negotiating, letters of intent, Wales, judicial interpretation, legislation, society, liability, drawing, limits on liability, literature review, drafting, case law, England, dispute, construction law |
| Subjects: | dispute resolution, technical documentation, contract formation, legal systems, data analysis and analytics, research methods, Geography, conflict resolution, liability law, construction law, communities and social development |
| Topics: | Legal Issues, Design Practice, Contract Administration, Research Practice, Geographical Context, Stakeholder Management |
| Descriptive scope: | 4 PCTA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here