Pareto analysis of critical risk factors of build operate and transfer projects in Nigeria

Waziri, B S (2018) Pareto analysis of critical risk factors of build operate and transfer projects in Nigeria. Journal of Construction Business and Management, 2(1), pp. 33-40. ISSN 2521-0165

Abstract

The need to meet the massive infrastructural gaps has led to the adoption of alternative procurement methods. Build Operate and Transfer (BOT) is one of the new ways used for procuring infrastructure. In developing countries, BOT projects are characterised by high-risk profile discouraging private investment. Therefore, it is imperative to identify the critical risk factors inherent in such arrangements with the view to attracting the desired level of private investment. This study employed Pareto Analysis to identify vital risk factors of BOT projects in Nigeria. Structured questionnaires were used to establish critical risk factors based on the perception of key stakeholders (government, concessionaire, lenders, and developers) in Abuja. Kaduna, Port Harcourt and Lagos. Descriptive statistics were used to obtain Standard Deviation of the risk factors indicating their impacts and severity. Based on the results, Pareto Analysis was carried out to separate the/'vital few' from the 'trivial many'. The results indicated nine risk factors as the vital few responsible for 80% contribution. The risk factors include; changes in government policies, hostile general business environment, project company default, time performance risk, cost performance risk, excessive development cost, instability in government, failure to raise finance for the project and lack of experience in handling the project. Therefore, for effective implementation of BOT projects, it is necessary for stakeholders to focus on the/'vital few' risk factors responsible for 80% of the risk impacts. The results of the study may not be generalised for use by clients and contractors operating in environments with different political and economic climate with Nigeria as the impact and likelihood of occurrence of risks may vary.

Item Type: Article
Uncontrolled Keywords: build-operate-transfer; Nigeria; Pareto analysis; questionnaire survey; risk factors
Index terms: questionnaire, time performance, cost performance, Abuja, default, concessionaire, developing country, survey, risk impact, risk factor, build-operate-transfer, Lagos, government policy, private investment, implementation, statistics, pareto analysis, procurement method, Nigeria, deviation
Subjects: economic analysis, financial and cost management, contractual arrangements, quality control, public policy, dispute resolution, contract type, mathematical modelling, data collection methods, environmental hazards, project controls, development economics, Geography, economics
Topics: Sustainability, Governance, Procurement, Research Practice, Geographical Context, Cost Management, Time Control, International Construction, Quality Management, Legal Issues
Descriptive scope: 4 PCEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here