Ssegawa, J K; Rwelamila, P D and Mogome, M G (2020) The challenges of closing construction projects final accounts in Botswana local authorities. Journal of Construction Business and Management, 4(1), pp. 13-23. ISSN 2521-0165
Abstract
Anecdotal information in the construction industry in Botswana indicated that the process of closing financial accounts for construction projects within a stipulated period is inefficient and ineffective. This is a serious industry problem because a project with an unclosed account is not a successful project as there are unfinished issues and claims left in abeyance to the detriment of both the client and contractor. This motivated a study aimed at investigating this aspect, including identifying the major causes of delays in formally closing final accounts of construction projects in local authorities. A multimethod approach consisting of a review of project documents which were beyond the end of the defect liability period were used in the study. Also, a questionnaire survey was administered to parties dealing with construction projects in the selected local authorities. Lastly, a focus discussion was held with key stakeholders who implement projects in some selected local authorities. Results indicated that while the final account closure process was inefficient (as only 42% of the accounts which were closed were finalised in the stipulated contractual time). Secondly, it was marginally effective (as only 54% of the sampled project accounts were closed). Common reasons for inefficiency and ineffectiveness include (i) contractors abandoning the project when they realise that the cost of rectifying the defects far exceeds the outstanding balance; (ii) clients taking too long to agree and approve final accounts; and (iii) loss of information when key personnel leave the project on the contractor's side before the final account is finalised. Despite the limitation of considering a selected number of local authorities' projects, the findings have confirmed anecdotal information circulating in the industry about the substantial numbers of project accounts that are usually left unclosed. The following recommendations based on the study results are made. That all adopted contract conditions be modified to focus on nipping the challenge in the bud as well as deterring instrument to future defaulters. The suggested modification: "it shall be mandatory for contractors to bring the project under tender to a formal closure through final account documentation within a specified period, defaulting contractors to be blacklisted from future contract awards in Botswana LAs". Ordinarily, since contractors can hardly suffer financial losses, the paper suggests that consultants and clients should objectively entertain contractors' claims arising from defects rectifications in the liability period. This is provided such defects were neither caused by poor materials nor are traceable to poor workmanship. These hopefully will mitigate the challenge, if followed.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | document analysis; final account; financial management; focus group; questionnaire survey |
| Index terms: | focus group, liability, personnel, documentation, survey, local authority, questionnaire, documents, construction project, workmanship, final account, financial management, contract condition, Botswana, document analysis, causes of delay, construction industry |
| Subjects: | data science, economic analysis, data collection methods, industry analysis, liability law, project controls, payment, sociology, contractual condition, Geography, production management, professional development, contract structure, management |
| Topics: | Business Strategy, Research Practice, Geographical Context, Project Management, Information Management, Stakeholder Management, Legal Issues, Human Resources, Time Control, Contract Administration |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here