Streamlining the management of payment delays: The case of Sri Lankan government building construction projects

Perera, B A K S and Dewagoda, K G (2020) Streamlining the management of payment delays: The case of Sri Lankan government building construction projects. Journal of Financial Management of Property and Construction, 26(2), pp. 236-256. ISSN 1366-4387

Abstract

Purpose: Delayed payments have been long standing, pressing issue in construction projects, especially in Government-funded construction projects. The root causes and the consequences of delayed payments must be identified before implementing strategies to mitigate the consequences of such delayed payments. However, these causes and consequences and the parties responsible for managing the delayed payments have not been identified so far. Therefore, the purpose of this study is to investigate the management of payment delays in Government-funded construction projects. Design/methodology/approach: The study used a mixed approach comprising four case studies and a questionnaire survey. The empirical data collected from the case studies and the questionnaire survey were analysed using manual content analysis and mean rating, respectively. Findings: The study identified the most significant causes and the most significant consequences of delayed payments that occur in Government-funded construction projects. It also revealed the strategies that clients, consultants, contractors and other parties can adopt to mitigate the adverse consequences of such delayed payments. Originality/value: This study identified the most significant causes of delayed payments in Government-funded construction projects, the most significant consequences of such delayed payments and the most suitable strategies the clients, consultants and contractors can adopt to mitigate the consequences of such delayed payments. Thus, this study supports streamlining the management of payment delays in Government construction projects and identifies the roles that different parties must play in managing payment delays in Government building projects, which is an under-researched area.

Item Type: Article
Uncontrolled Keywords: causes; consequences; delayed payments; government construction projects; strategies
Index terms: strategy, content analysis, building construction, survey, construction project, methodology, questionnaire, streamlining, case study
Subjects: data analysis and analytics, data collection methods, building construction, production management, research methods, management
Topics: Project Management, Research Practice, Business Strategy, Construction Technology
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here