Badenfelt, U (2007) Trust and control in the early phases of target cost contracts. In: Boyd, D (ed.) Proceedings of 23rd Annual ARCOM Conference, 3-5 September 2007, Belfast, UK.
Abstract
Target cost contracts entail the use of open book accounting, giving the client full access to project costs. Since comprehensive cost control is expensive, other less costly control mechanisms might be better for the client. Moreover, the ambiguous connection between control and trust and the negative impact of control on the collaboration climate is well known. The purpose of this paper is to investigate the variety of control mechanisms used by the client in the early phases of a target cost contract and give a deeper understanding of the complex relationship between trust and control. A case study approach is adopted, which demonstrates the control mechanisms used by the client in a construction project in order to guarantee that the contractor behaves in a trustworthy way. The case is a large laboratory project with a target cost contract, where the empirical data were gathered through interviews and non-participant observations. Based on previous experiences the client considered the contractor as reliable and believed that a rigorous control of project costs might hurt the relationship. However, the client’s opinion was that trust is fragile and must be continuously preserved. Therefore the client analyses the contractor’s response to project changes as a measure of contractor reliability. For instance, if there are any strange features in the contractor’s response, or if the contractor behaves in a suspicious way, the client might find it necessary to expand control, even if it might impact negatively on the collaboration climate.
| Item Type: | Conference Paper (Paper) |
|---|---|
| Uncontrolled Keywords: | control; open book accounting; target cost contract; trust |
| Index terms: | cost control, collaboration, construction project, accounting, interview, laboratory, observation, guarantee, case study, project cost, target cost |
| Subjects: | data collection methods, financial and cost management, economic analysis, production management, management, contract structure, economics, research management |
| Topics: | Organizational Design, Cost Management, Business Strategy, Project Management, Research Practice, Procurement |
| Descriptive scope: | 3 PCE |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here