An expert system prototype for construction planning and productivity analysis

Boussabaine, A (1991) An expert system prototype for construction planning and productivity analysis. PhD thesis, University of Manchester, UK.

Abstract

The identification and specification of construction operations and the selection of construction methods, including equipment and labour resources, are central activities in the production planning of construction projects. The decisions taken are complex and the choice of construction method and estimate of production output have serious consequences for the effectiveness of programming in achieving the most economic and practicable solution production planning problems. Improving construction productivity by detailed and accurate planning is critically important in the increasingly competitive environment of the construction industry. Mathematical or statistical models of factors affecting production output together with knowledge based systems, available to the planner through the medium of the micro-computer, could be valuable tools by which to improve planning and productivity and hence minimise the costs of construction. In this thesis aspects of construction planning are discussed and opportunities identified for the application of a knowledge based system to interface with conventional network programming computer software. The development of a prototype system to help the planner in generating construction activities and their logical relationships, and in estimating activity durations, is described. The system uses a knowledge base of construction activities and factors affecting productivity to assist the user in the preparation of input files for his CPM program. The knowledge structure of the prototype system is composed of frames, production rules and procedures. The frames consist of facts used to represent the structure hierarchy of activities, the formalised task precedence relationships, description of construction tasks and the information about the productivity factors. The production rules are heuristics used to determine the breakdown of activities into scheduling tasks and precedence of activities, and to quantify productivity factors. The procedures are used for activity durations estimation, generating reports, interfacing with the network program and to carry out a Monte Carlo simulation to determine cumulative probability distributions of activity duration. The results of this pilot system have shown that the system can be an effective productivity estimation tool for construction planners. The ability of the system to improve the quality of construction schedules further suggests that the model developed is rigorous enough to warrant its continued development into a commercial system.

Item Type: Thesis (Doctoral)
Uncontrolled Keywords: commercial; construction method; construction planning; duration; equipment; estimating; labour resources; production planning; productivity; programming; scheduling; Monte Carlo simulation; probability
Index terms: production planning, construction method, prototype, specification, scheduling, knowledge base, estimating, precedence relationship, programming, construction planner, expert system, program, construction project, estimation, probability distribution, construction operation, Monte Carlo simulation, knowledge-based system, construction activity, productivity, heuristic, labour resource, construction planning, statistical model, construction industry, construction productivity, duration, estimate, planner, effectiveness
Subjects: operations management, modelling and simulation, operations research, project delivery, financial and cost management, construction planning, artificial intelligence, data science, construction operations, risk assessment, profession, practitioner, programming, building construction, data management, project controls, business economics, information systems, statistical analysis, industry analysis, software systems, performance management, management, production management, contractual condition
Topics: Quality Management, Digital Applications, Time Control, Contract Administration, Site Management, Engineering Principles, Research Practice, Project Management, Cost Management, Business Strategy, Risk Management, Roles and Professions
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here