Pan, N-F S (2001) Fuzzy reasoning expert scheduling system (FRESS) for highway construction subject to rain impact: A case study in Taiwan. PhD thesis, Ohio State University, USA.
Abstract
In Taiwan, more and more construction projects adhere to calendar-day-based contracts, whereby the construction contractor will be taking more risks than ever before. Construction scheduling contains uncertainties such as conditions of weather and site, and performance of equipment and labor. Among these uncertainties, rainfall is regarded as a major factor that has severe adverse impact on productivity and duration of highway construction projects. The most common approach for schedulers to account for the effect of rain in Taiwan is by adding a percentage of time to activities based on time of year and type of activity. However, this procedure may not be uniformly applied to all the activities. In addition, the precise effect of rain is difficult to assess and evaluate because it is usually expressed qualitatively rather than quantitatively. Moreover, schedulers usually estimate rain influence based on their past experience in a similar situation. However, their experience is often limited to particular project types, locations, and rainfall patterns. Thus, a more accurate and reliable method is necessary to assist construction schedulers. This study presents a model to estimate the impact of rain on productivity and duration of highway construction, taking into account linguistic variables such as rainfall level, soil drainage, exposure level of an activity, and work or no-work. This model employs the techniques of expert system, fuzzy set and Mamdani's fuzzy reasoning method. An expert system is utilized because the estimates of activity duration are usually made by experienced schedulers. Fuzzy set theory and fuzzy logic are applied because rain effect is usually expressed linguistically. Based on the model, an intelligent system, named FRESS (Fuzzy Reasoning Expert Scheduling System), is developed for estimating rain influence before and during construction for scheduling, and after construction for claim analysis of delay. FRESS interfaces with the Kappa-PC expert system shell and MS-Project scheduling package, which provides a user-friendly interface. This system contains a knowledge base and database. The knowledge base consists of if-then production rules, obtained from experts in highway construction. The database includes historical daily rainfall data over the past 20 years for nine major cities across Taiwan. A real-world highway construction project is utilized to illustrate the essential features of the system and demonstrate its performance and effectiveness, which can provide construction schedulers accurate and reasonable schedules.
| Item Type: | Thesis (Doctoral) |
|---|---|
| Thesis advisor: | Hadipriono, F C and Whitlatch, E |
| Uncontrolled Keywords: | duration; effectiveness; fuzzy set; reasoning; construction project; drainage; equipment; highway; estimating; expert system; productivity; scheduling; Taiwan; fuzzy logic; weather |
| Index terms: | expert system, construction project, weather, estimating, exposure, drainage, construction contractor, scheduling, project scheduling, Taiwan, reasoning, rainfall, scheduler, knowledge base, effectiveness, rain, highway construction, estimate, duration, package, case study, construction scheduling, fuzzy logic, database, fuzzy set, intelligent system, fuzzy set theory, productivity |
| Subjects: | practitioner, climate science, air quality, data collection methods, financial and cost management, contractual arrangements, data science, operations research, Geography, production management, automation and robotics, performance management, civil engineering, public and environmental health, management, information systems, infrastructure and transport systems, decision-making and optimization, cognitive psychology, project controls, data management |
| Topics: | Quality Management, Procurement, Sustainability, Project Management, Geographical Context, Engineering Principles, Health and Safety, Time Control, Digital Applications, Roles and Professions, Research Practice, Business Strategy, Cost Management |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here