Change orders impact assessment for labor intensive construction

Gunduz, M (2002) Change orders impact assessment for labor intensive construction. PhD thesis, University of Wisconsin - Madison, USA.

Abstract

Aggressive scheduling for construction projects is becoming increasingly common in project management because of tight budgets and the client's desires to commence operations quickly. This has led to an increase in the chances and magnitude of project change. Two types of costs are associated with the change orders, direct and impact costs. Direct cost is the original budget, which the project was planned and scheduled for. Impact cost is the negative budget or time influences that the changes or alterations may have on the rest of the project. It causes the contractor to alter the planned sequence of work, use inefficient methods, work in a later time frame, prolong work and, in some cases, stop the work. The research had managerial and quantitative objectives: (1) To develop a quantitative relationship between %Delta (Loss of productivity) and several independent variables for small projects. Small projects are not studied in the existing literature. (2) To develop a regression model to predict that a project would be impacted by change orders in the bidding stage. (3) To identify project characteristics that indicate a project has been impacted using hypothesis testing. (4) To define a quantitative relationship between delay vs. change order. (5) To summarize research findings as recommendations for industry and future research. A list of factors that influence change orders and project performance was determined. These factors were statistically analyzed to represent some early warning signs for contractors to attend to avoid bidding for projects that are likely to be impacted by changes. Several special models were also developed to quantify the impact of change orders on labor productivity for small projects. Hypotheses were developed to capture impact related project factors. Regression models were used as necessary for quantification of the hypothesis and the proposed models. The study was completed by providing owners and contractors with a list of best practices on how to reduce the impact of change orders.

Item Type: Thesis (Doctoral)
Thesis advisor: Hanna, A S
Uncontrolled Keywords: construction project; best practice; bidding; productivity; scheduling; client; owner; project performance; quantification
Index terms: labour productivity, project performance, best practice, small project, project management, testing, direct cost, becoming, quantification, regression model, change order, owner, independent variable, productivity, impact assessment, construction project, bidding, scheduling, early warning
Subjects: business, value management, operations research, bidding, professional practice, management, economics, contractual condition, production management, project management theory and practice, financial risk, measurement and scaling, sociology, philosophical process, statistical analysis
Topics: Engineering Principles, Project Management, Procurement, Site Management, Contract Administration, Time Control, Research Practice, Cost Management, Business Strategy, Stakeholder Management
Descriptive scope: 3 PCA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here