Cosma, C (2003) Development of a systematic approach for uncertainty assessment in scheduling multiple repetitive construction processes by using fuzzy set theory. PhD thesis, University of Florida, USA.
Abstract
A growing portion of the U.S. Interstate highway system needs major rehabilitation and/or reconstruction. Many highway segments are located in or near major urban corridors serving high traffic volumes throughout the day and performing as critical links for local and through traffic. Shutting down a highway segment for rehabilitation and/or reconstruction work for extended periods of time will have as consequences considerable inconvenience and increased delays for road users, major community disruption, and significant economic loss. Applications of procedures to improve planning, scheduling, and control of highway construction and maintenance projects can reduce these inconveniences. In order to achieve significant reductions in highway construction project times a broader, systematic approach to the problem is proposed. Planning and scheduling of transportation construction projects is facilitated using the linear scheduling method (LSM) because of its visual and intuitive capabilities. One of the main problems with LSM is that to date there is no formal method developed that could allow LSM to determine uncertainties in time completion. In engineering, uncertainties can be attributed mainly to ambiguity, likelihood, approximations and inconsistency. Several formal techniques for managing the different types of uncertainty have been developed but there has not been any consensus on the appropriateness of such techniques so far. It seems that there is no best theory of uncertainty and therefore the choice of the most appropriate technique depends upon the specific problem. In response to these problems the fuzzy set theory is utilized to propose an efficient and systematic procedure for uncertainty assessment. The assessment procedure proposed is a heuristic tool that can process linguistic terms as used by experts allowing the quantification of expert knowledge in estimating and assessing uncertainty in scheduling repetitive construction projects.
| Item Type: | Thesis (Doctoral) |
|---|---|
| Thesis advisor: | Herbsman, Z J |
| Uncontrolled Keywords: | fuzzy set; uncertainty; construction project; highway; traffic; estimating; rehabilitation; repetitive construction; scheduling; heuristic; quantification |
| Index terms: | repetitive construction, fuzzy set theory, heuristic, highway construction, linear scheduling, scheduling, reconstruction, construction project, fuzzy set, estimating, quantification |
| Subjects: | risk assessment, building construction, financial and cost management, measurement and scaling, civil engineering, decision-making and optimization, operations research, production management |
| Topics: | Research Practice, Cost Management, Project Management, Risk Management, Engineering Principles, Time Control, Construction Technology |
| Descriptive scope: | 4 PCTA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here