Quantifying the impact of schedule compression on construction labor productivity

Chang, C-K (2004) Quantifying the impact of schedule compression on construction labor productivity. PhD thesis, University of Wisconsin - Madison, USA.

Abstract

The reduction of time available to complete a project is commonly known throughout the construction industry as schedule compression. Schedule compression is a problem because it negatively impacts labor productivity in various ways, and it becomes a source of dispute between the owners and contractors. Exacerbating the problem is the fact that schedule compression is a common occurrence on construction projects. Furthermore, the court recognizes that contractors usually fail to show a cause-effect relationship between the schedule compression and increased cost. Without demonstrating damages and being able to quantify them, the additional cost of lost productivity can not be compensated. The objectives of this research were to investigate and quantify the impact of the three most common schedule compression methods: overtime, overmanning, and shift work on construction labor productivity, and to develop a model that quantifies the total impact of schedule compression on labor productivity at the project level. The first objective was achieved by developing quantification models for each respective method. The second objective was achieved by introducing a quantitative definition of schedule compression that compares actual project duration to its corresponding normal duration for the same type and size of a project, and developing a logistic regression model that determines whether a project was impacted by schedule compression and a quantification model that quantifies the total impact of schedule compression on labor productivity. The application process provided in chapter six and the models developed in this study can provide guidance for contractors and owners and for resolving disputes that arise about lost productivity caused by schedule compression, and best practices provided at the end of this study will identify ways to mitigate productivity loss from schedule acceleration and compression.

Item Type: Thesis (Doctoral)
Thesis advisor: Hanna, A S
Uncontrolled Keywords: duration; construction project; best practice; disputes; productivity; owner; quantification
Index terms: labour productivity, schedule acceleration, construction labour, best practice, construction industry, duration, logistic regression, quantification, dispute, productivity, owner, construction project, schedule compression, compression, damages
Subjects: project controls, sociology, measurement and scaling, industry analysis, statistical analysis, management, production management, material properties and characteristics, operations research, business, dispute resolution
Topics: Project Management, Legal Issues, Business Strategy, Construction Materials, Research Practice, Stakeholder Management, Time Control, Site Management
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here