Quantification and analysis of construction claims

Mbabazi, A (2004) Quantification and analysis of construction claims. PhD thesis, University of Waterloo, Canada.

Abstract

With the construction market being increasingly competitive, contractors have increasingly submitted optimistic bids; as a result, many projects experience delays and cost overruns. This often leads to claims and disputes. Quantifying and resolving construction claims, consequently, has become an inevitable routine for both the contractor and owner staff. Winning a claim depends on the ability to prove: legal responsibility, project delay, and claim amount. Lack of knowledge and tools to quantify these three claim elements is a major problem for the construction industry. This study proposes a reliable and accurate method to quantify and analyse construction claims. The relative frequency of the leading claim causes is estimated at: defective contract documents (27%), differing site conditions (15%), work changes (15%), and weather (3%). Through a comprehensive literature review and analysis of 100 court cases, factors affecting legal responsibility for these claim causes are identified. A decision support tool that uses a set of decision rules is developed to assess legal responsibility for a claim event. Existing methods to calculate and apportion responsibility for project delays are evaluated and found inadequate. Accordingly, two new reliable and accurate delay analysis methods are developed (Modified But-For and Daily Windows Analysis method). With regard to cost consequences, claim amount is calculated based on: contract terms, breach of contract, tort liability, and qualitative considerations. Based on the developed methods, an integrated computer program is developed to assess legal responsibility, calculate and apportion project delay, and maximise claim amount.

Item Type: Thesis (Doctoral)
Thesis advisor: Hegazy, T and Saccomanno, F
Uncontrolled Keywords: cost overrun; decision support; liability; market; contract terms; disputes; owner; delay analysis; weather
Index terms: contract term, quantification, owner, dispute, cost overrun, computer program, construction market, construction industry, liability, decision support, routine, breach of contract, literature review, delay analysis, contract document, window, project delay, weather, construction claim
Subjects: dispute resolution, air quality, data analysis and analytics, financial and cost management, contractual condition, architectural elements, software systems, industry analysis, liability law, payment, project controls, market analysis, measurement and scaling, decision analysis, sociology
Topics: Organizational Design, Contract Administration, Time Control, Design Practice, Digital Applications, Stakeholder Management, Cost Management, Research Practice, Legal Issues, Risk Management, Sustainability
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here