Aggiag, M A A (2005) The impact of client attributes on project success: a study of UK public construction projects. PhD thesis, Northumbria University, UK.
Abstract
In the literature that deals with the causes of time and cost overruns in building construction there is a certain amount that highlights the role of the client. However, most studies are limited in their approach and they do not fully recognise the potential association between client-related attributes and project success in building projects. In fact, the challenge of investigating client-related attributes in public-sector building projects is of vital importance if society is to gain the high-quality, cost-effective municipal buildings of the future. The selection of the client as the main focus in this research project came as a consequence of the author's working experience. An intensive literature search then showed that only a limited number of studies had examined the client's attributes in relation to project success. The study's results indicate that the client and its project manager are essential factors in driving project outcomes. Unified organisation, and consistent actions and attitudes of the client organisation are crucially linked to keeping the schedule and budget within their limits and ensuring project functionality. Project functionality was also associated with the client's level of proficiency. In the case of the client's project manager, its actions, attitudes, proficiency and experience appear less likely to affect the duration of the project, but are critical in reducing cost and improving the project's functionality. It also appears that the procurement types used within the surveyed projects had an influence on these associations. The findings underlined the major role that clients have to play in constructing public buildings. More consideration has to be taken by clients as to their actions and attitudes during the process of building construction; furthermore, they have to be aware that any changes in their organisation might affect project outcomes. Clients should choose their project manager carefully given that consistent actions, attitudes, proficiency and experience of the project manager are key elements in attaining the successful completion of projects.
| Item Type: | Thesis (Doctoral) |
|---|---|
| Thesis advisor: | Greenwood, D; Osborne, A and Hogg, K |
| Uncontrolled Keywords: | client; procurement; project manager; project success; survey |
| Index terms: | cost overrun, project success, functionality, duration, society, building construction, project manager, public building, project outcome, client organization, survey, public construction |
| Subjects: | financial and cost management, project completion, communities and social development, building construction, project management theory and practice, construction type, project controls, client relations, profession, data collection methods, design features |
| Topics: | Time Control, Research Practice, Cost Management, Project Management, Construction Technology, Engineering Principles, Roles and Professions, Stakeholder Management, Design Practice |
| Descriptive scope: | 3 PCE |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here