Stochastic modelling and analysis of construction processes

Graham, D P (2005) Stochastic modelling and analysis of construction processes. PhD thesis, University of Edinburgh, UK.

Abstract

Construction projects frequently overrun and finish over budget; in part due to the lack of control that construction practitioners have over the construction schedule at a process level. Planning methods such as CPM are not of sufficient detail to allow a practitioner to plan a process to maximise its performance. Thus the aim of this research was to develop a practical, computer-based model to enable practitioners to plan projects at a process level and hence improve their projects. This research has focused upon a specific type of process - those that are stochastic and cyclical. Such processes are difficult to predict and hence control, and they are widespread throughout construction projects. Examples are crane operations, formwork erection and scaffold erection. Initially, a focus was placed on the ready-mixed concrete (RMC) supply process. A discrete event simulation (DES) model of this process was developed and validated, based upon real project data. This model could not provide accurate estimates of the process due to the requirement that a user define the probability distributions that represent the process. This is a complex requirement for a practitioner, the issue became known as the complexity problem and a solution was sought using case-based reasoning (CBR). CBR provides solutions to new problems using knowledge from past ones - exactly what a practitioner was doing in the above simulation model. CBR was shown to be capable of solving the complexity problem. A hybrid model, <i>CBRSim, </i>was formed to fulfil the original aim of this thesis. <i>CBRSim </i>works by: CBR selecting probability distributions (based on user input) that are used in a DES model to accurately recreate the process. CBRSim was validated and modelled the process to within +/- 3% accuracy. <i>CBRSim </i>was then applied to another stochastic and cyclical construction process: earthmoving. <i>CBRSim </i>was found to be more accurate in estimating earthmoving productivity than RMC supply, thus providing an indication of a generic modelling capability.

Item Type: Thesis (Doctoral)
Uncontrolled Keywords: accuracy; case-based reasoning; complexity; concrete; construction project; crane; estimating; formwork; probability; productivity; reasoning; simulation
Index terms: reasoning, estimating, complexity, planning method, construction project, formwork, accuracy, overrun, discrete event simulation, project data, estimate, construction process, modelling, productivity, construction practitioner, earthmoving, case-based reasoning, practitioner, probability distribution
Subjects: building construction, data collection methods, analytical methods, professional development, project controls, statistical analysis, management, financial and cost management, production management, modelling and simulation, systems engineering, urban planning, practitioner, cognitive psychology, construction operations
Topics: Project Management, Research Practice, Governance, Construction Technology, Site Management, Roles and Professions, Time Control, Information Management, Business Strategy, Cost Management, Engineering Principles
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here