Vaziri, K (2006) Program planning under uncertainty. PhD thesis, Cornell University, USA.
Abstract
The purpose of this dissertation is to provide the means for program managers to optimally allocate resources from common resource pools to individual tasks on several competing projects. Instead of the traditional use of schedules, we develop control policies in the form of planned resource allocation to tasks that capture the uncertainty associated with task durations and the impact of resource allocation on those durations. This dissertation is organized into three chapters. The focus of chapter one is the development of a model and a solution procedure for resource allocation across projects when there are significant uncertainties associated with the task durations and the resource needs of individual tasks. This chapter makes two significant contributions to the literature on project management. First, it creates a mathematical model that captures the uncertainty associated with task durations and resource requirements. Second, it develops a solution procedure that allocates available resources to tasks. The procedure is sensitive to the relationship between the resources allocated to a task and the probability distribution for the duration of the task. We use simulation to capture the risk associated with the resource assignments to tasks. The second chapter is built on the findings of the first chapter and applies the concepts developed in the first chapter to the specific needs of the construction industry. This chapter makes four significant contributions to the literature in project management for construction activities. First, it creates a mathematical formulation and solution procedure that captures the uncertainty associated with task duration and resource requirements that are sensitive to the particular characteristics of construction activities. Second the model includes an explicit mechanism to explore the consequences of cross-functioning personnel. Third, it creates a mechanism to understand the value of re-planning worker assignments as the projects unfold. Fourth, a complex case study is developed illustrating how to use the model in practice. The focus of the third chapter is the refinement and computational evaluation of a solution procedure based on chapter one for resource allocation across projects when there are significant uncertainties associated with the task durations and the resource needs of individual tasks.
| Item Type: | Thesis (Doctoral) |
|---|---|
| Thesis advisor: | Nozick, L K |
| Uncontrolled Keywords: | duration; personnel; uncertainty; resource allocation; probability; case study; simulation |
| Index terms: | mathematical model, manager, personnel, program, probability distribution, construction activity, case study, resource allocation, project management, construction industry, duration, dissertation |
| Subjects: | construction operations, resource management, research dissemination and communication, data collection methods, mathematical modelling, practitioner, project controls, industry analysis, statistical analysis, management, software systems, project management theory and practice |
| Topics: | Project Management, Time Control, Site Management, Human Resources, Digital Applications, Roles and Professions, Research Practice |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here