How differences in heavy civil project set-up practices impact performance

Yearsley, W S (2007) How differences in heavy civil project set-up practices impact performance. PhD thesis, Colorado State University, USA.

Abstract

The life cycle of a construction project traditionally involves five phases: procurement, pre-construction planning, execution, closeout, and maintenance. The second phase, pre-construction planning is broad in nature yet vital to achieving a successful project. This study is unique in its focus on the contractors' perspective of pre-construction planning in the heavy civil sector. Data utilized was derived from a national survey developed specifically for this research. A mailed questionnaire was sent to 1,334 senior executives nationally, of whom 121 responded. Participants were asked to respond to questions about the individual characteristics of their companies including financial performance. They then responded to a series questions asking them to rate how often they practiced specific project set-up activities. Project set-up activities were categorized into groups from which composite variables were developed. These composite variables were utilized to study the relationships between how often certain project set-up activities were practiced and their contribution to over-all company performance expressed as profit margin (earnings before interest and tax or EBIT). Multiple-regression, factor analysis and frequency analysis were used for evaluating this data. The descriptive responses were utilized to evaluate differences in patterns of variance based on individual company characteristics. Hierarchical cluster analysis was utilized to assess these relationships. Only a partial relationship was found between how often certain project set-up activities were practiced and over-all performance. Project set-up activities concerning the identification of risk and opportunities accounted for the majority of the relationships found. Individual company characteristics did not significantly correlate to patterns of variance in performance and which activities were practiced. Supplementary analysis contrasting mean scores from high margin companies with lesser performing peers yielded differences in how often project set-up activities are practiced. This research provides insights as to which project set-up activities are most often practiced by top performing construction companies. These insights provide a guide for construction contractors to consider as they look toward planning future projects. While only partial correlations to over-all performance were found in this research the door has been opened for further study.

Item Type: Thesis (Doctoral)
Thesis advisor: Cobb, B
Uncontrolled Keywords: construction project; life cycle; cluster analysis; factor analysis; construction contractor
Index terms: questionnaire, cluster analysis, construction project, financial performance, construction contractor, profit, construction company, senior executive, factor analysis, multiple-regression, composite, national survey, variance, pre-construction, life cycle
Subjects: business analysis, production management, measurement and scaling, statistical analysis, leadership, organization, data collection methods, value management, practitioner, materials science, research products and data, economic analysis, project delivery, data analysis and analytics
Topics: Project Management, Human Resources, Research Practice, Construction Materials, Business Strategy, Roles and Professions
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here