Braimah, N (2008) An investigation into the use of construction delay and disruption analysis methodologies. PhD thesis, University of Wolverhampton, UK.
Abstract
Delay and disruption (DD) to contractors' progress, often resulting in time and cost overruns, are a major source of claims and disputes in the construction industry. At the heart of the matter in dispute is often the question of the extent of each contracting party’s responsibility for the delayed project completion and extra cost incurred. Various methodologies have been developed over the years as aids to answering this question. Whilst much has been written about DD, there is limited information on the extent of use of these methodologies in practice. The research reported in this thesis was initiated to investigate these issues in the UK, towards developing a framework for improving DD analysis. The methodology adopted in undertaking this research was the mixed method approach involving first, a detailed review of the relevant literature, followed by an industry-wide survey on the use of these methodologies and associated problems. Following this, interviews were conducted to investigate the identified problems in more depth. The data collected were analysed, with the aid of SPSS and Excel, using a variety of statistical methods including descriptive statistics analysis, relative index analysis, Kendall’s concordance and factor analysis. The key finding was that DD analysis methodologies reported in the literature as having major weaknesses are the most widely used in practice mainly due to deficiencies in programming and record keeping practice. To facilitate the use of more reliable methodologies, which ensure more successful claims resolution with fewer chances of disputes, a framework has been developed comprising of: (i) best practice recommendations for promoting better record-keeping and programming practice and; (ii) a model for assisting analysts in their selection of appropriate delay analysis methodology for any claims situation. This model was validated by means of experts' review via a survey and the findings obtained suggest that the model is valuable and suitable for use in practice. Finally, areas for further research were identified.
| Item Type: | Thesis (Doctoral) |
|---|---|
| Uncontrolled Keywords: | contract; delay analysis; disruption analysis; interview; questionnaire survey |
| Index terms: | contracting party, cost overrun, dispute, mixed method, statistics, resolution, construction industry, heart, statistical method, factor analysis, investigation, best practice, survey, interview, programming, questionnaire, delay analysis, construction delay, methodology |
| Subjects: | medical science and clinical practice, research methods, industry analysis, statistical analysis, conflict resolution, project controls, programming, practitioner, dispute resolution, data collection methods, business, mathematical modelling, financial and cost management |
| Topics: | Health and Safety, Legal Issues, Roles and Professions, Stakeholder Management, Research Practice, Business Strategy, Cost Management, Time Control, Digital Applications |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here