Kasim, N B (2008) Improving materials management on construction projects. PhD thesis, Loughborough University, UK.
Abstract
An essential factor adversely affecting the performance of construction projects is the improper handling of materials during site activities. Materials management is made problematic by materials shortages, delays in supply, price fluctuations, damage and wastage, and lack of storages pace. In addition, paper-based reports are mostly used to record and exchange information related to the materials component within a supply chain which is problematic, error-prone, and inefficient. Generally, modem technologies are not being adequately used to overcome human error and are not well integrated with project management systems to make the tracking and management of materials easier and faster. Thus, this research focuses on the development of a mechanism to improve materials management on construction projects through the integration of materials tracking and resource modelling systems. A multi-facetted research approach was adopted. Initially, a literature review on materials management process in the construction project was conducted. This was followed by case studies involving six construction projects in order to investigate current practice in materials management to establish key problem areas and elements of good practice. The case studies also explored the requirements for integrating materials management and resource modelling in project management systems. The case study findings underpinned by literature results were used to develop a real-time framework for integrating RFID-based materials tracking and resource modelling. The framework was encapsulated in a computer-based prototype system based on Microsoft Visual Basic. NET. The prototype system was developed by amalgamation of all the software and hardware chosen such as MS Access (database system), MS Project (resource modelling) and RFID (automated materials tracking) to provide the mechanisms for integrating materials management and resource modelling in the construction industry. Evaluation of the prototype system was carried out by a series of interviews with industry practitioners to assess its appropriateness and functionality. It also established the skills and other requirements for the effective use of the real-time materials tracking system. The evaluation established that the prototype system demonstrated many benefits and is suitable for use in materials tracking and inventory management processes. It is concluded that the prototype system developed can improve materials management on construction projects, particularly with regard to materials tracking and integrating materials utilisation with the resource modelling subsystem in project management applications. Adoption of the approaches suggested in the thesis will enable the construction industry to improve the real-time management of materials on sites, and hence improve project performance.
| Item Type: | Thesis (Doctoral) |
|---|---|
| Uncontrolled Keywords: | case study; materials management; prototype testing; radio frequency identification |
| Index terms: | interview, functionality, literature review, prototype, practitioner, construction project, integration, materials management, shortages, radio frequency identification, case study, inventory, time management, good practice, database, project performance, hardware, project management, construction industry, testing, modelling |
| Subjects: | analytical methods, economic analysis, professional practice, data analysis and analytics, operations management, design features, modelling and simulation, digital technology, practitioner, computer hardware, data collection methods, industry analysis, organizational analysis, project controls, data management, project management theory and practice, production management, inventory management, performance measurement |
| Topics: | Supply Chain Management, Quality Management, Engineering Principles, Project Management, Digital Applications, Design Practice, Organizational Design, Site Management, Time Control, Research Practice, Roles and Professions |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here