Analyses of highway project construction risks, performance, and contingency

Diab, M F (2011) Analyses of highway project construction risks, performance, and contingency. PhD thesis, North Dakota State University, USA.

Abstract

Past studies have highlighted the importance of risk assessment and management in construction projects and transportation industry, and have identified cost and time as the most important risks that transportation professionals want to understand and manage. The main focus of this study is to comprehensively analyze transportation construction risk drivers and identify the correlation of the significant risk drivers with project characteristics, cost growth, schedule growth, and project contingency. This study has adopted 31 relevant and significant programmatic and project-specific risk drivers from different past studies. These risk drivers have been analyzed and evaluated using survey responses from professionals in the context of highway transportation projects. Risk assessments including rating of the encountered risk drivers and their correlation with project characteristics have been carried out within the context of highway construction projects in the United States. Correlations of the construction project performance or risk measures, cost growth percentage, and schedule growth percentage, with the rating values of identified risk drivers values have enabled a better understanding of the impacts of risks and the risk assessment process for highway transportation projects. The impact of significant risk drivers on reported construction cost contingency amounts has also been analyzed. The purpose of this effort was to assess impact of ratings for cost impact, schedule impact, and relative importance of the identified risk drivers on contingency amounts. Predetermined method is the common way to calculate contingency amount in transportation projects. In this study parametric modeling has been used to analyze the relationship between predetermined contingency amounts in transportation projects with perceived risk rating values in order to understand how the expert judgments regarding risk ratings can be used in determination of contingency amounts.

Item Type: Thesis (Doctoral)
Uncontrolled Keywords: construction cost; construction project; contingency; expert judgment; highway; performance; risk assessment; professional; project performance; United States
Index terms: judgment, construction cost, project performance, schedule growth, risk assessment, highway construction, modelling, relative importance, United States, survey, transportation project, construction project
Subjects: dispute resolution, risk assessment, data collection methods, analytical methods, financial and cost management, Geography, production management, project management theory and practice, financial risk, civil engineering, infrastructure and transport systems, project controls
Topics: Time Control, Research Practice, Cost Management, Legal Issues, Engineering Principles, Project Management, Geographical Context, Risk Management
Descriptive scope: 3 PCE

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here