Hollar, D A (2011) Predicting preliminary engineering costs for highway projects. PhD thesis, North Carolina State University, USA.
Abstract
Preliminary engineering (PE) for a highway project encompasses two efforts: planning to minimize the physical, social, and human environmental impacts of projects and engineering design to deliver the best alternative. State transportation agencies strive to manage these efforts efficiently, seeking to maximize the utilization of limited funding and workforce productivity. Managers need a feasible PE budget early in project development. The results reported herein will enable engineers and managers to develop PE budgets during the preconstruction phase of highway project development. Typically, transportation managers establish a project's PE budget using a percentage of estimated project construction costs disregarding other project-specific parameters. The commonly accepted rule of thumb for PE costs is 10% of estimated construction costs. This research effort sought to improved PE cost estimation methods by investigating available historical data supporting statistical analyses, developing predictive regression models forecasting projects' PE costs, and assessing model performance through validation. Cost data were acquired for 461 bridge projects and 188 roadway projects let for construction between 1999 and 2009 in North Carolina. Separate analyses were performed on bridges and roadways. Both project types are included in North Carolina's State Transportation Improvement Program. Many variables applicable for bridges were not applicable or available for roadways. Analysis of the roadway data yielded a mean ratio of PE cost to estimated construction cost (the PE cost ratio) of 11.7%. Comparatively, the bridge projects exhibited a mean PE cost ratio of 27.8%, approximately 2.4 times greater than the roadway mean. Using multiple linear regression and hierarchical linear modeling, we developed prediction models to forecast the PE cost ratio of future bridge and roadway projects. Before model development began, we randomly selected a portion of the data for validation. Regression modeling used the remainder of the data. Validation of the bridge model (using 70 projects) resulted in a mean absolute percentage error (MAPE) of 43%. The bridge model utilized eight variables, four numerical and four categorical, with interactions. When validating on 38 roadway projects, the roadway model yielded an average absolute error (AAE) of ± 6.91%. Considering the roadway database exhibited a mean PE cost ratio of 11.7%, this AAE represents a 59% relative error. Comparatively, predictive regression modeling did yield better PE cost estimates than using the commonly accepted rule of thumb, or any single parameter estimator. However, the relative error was high, in the 40% to 60% range. Example calculations using the developed models (bridge and roadway) are presented. Improvements to agency preconstruction cost accounting and tracking processes would support better modeling efforts. Lack of consistent historical data influenced our model development. Others pursing PE cost analyses should thoroughly evaluate and assess data quality before initiating similar modeling efforts.
| Item Type: | Thesis (Doctoral) |
|---|---|
| Thesis advisor: | Liu, M; Rasdorf, W and Hummer, J E |
| Uncontrolled Keywords: | construction cost; construction phase; environmental impact; funding; highway; workforce; cost estimation; forecasting; productivity; estimator; validation |
| Index terms: | agency, accounting, model development, estimator, validation, environmental impact, program, prediction model, regression modelling, cost estimating, cost analysis, manager, project development, construction phase, modelling, interaction, bridge project, cost data, cost estimate, engineering design, funding, highway construction, database, statistical analysis, construction cost, engineer, transportation agency, productivity, forecasting, regression model |
| Subjects: | data science, prediction and forecasting, financial and cost management, project delivery, profession, infrastructure and transport systems, statistical analysis, data management, sociology, professional development, management, civil engineering, software systems, economic analysis, analytical methods, environmental impact, practitioner, behavioral psychology, transportation engineering, design process, accounting and finance |
| Topics: | Project Management, Engineering Principles, Sustainability, Digital Applications, Research Practice, Information Management, Business Strategy, Cost Management, Roles and Professions |
| Descriptive scope: | 4 PCTA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here