Predicting cost overrun of railroad bridge construction

Attara, M G (2015) Predicting cost overrun of railroad bridge construction. PhD thesis, Rutgers The State University of New Jersey - New Brunswick, USA.

Abstract

Railroad Bridge Construction Projects have frequently exceeded their cost and schedule resulting in major financial losses to the owners and to the contractors, severe interruption of the rail operation schedules and consequently significant inconvenience to the rail commuters. Currently, there are very few methods available to predict the completed construction cost. This research proposes cost estimating model that incorporates the “major uncertainty constraints” (MUC) which drive both the cost and schedule of Railroad bridge Construction. This approach is an advanced unique model that is proposed for calculation of adequate contingency in a portfolio of construction projects. It is used to update historical contingency values based on new railroad project data that becomes available as soon as construction projects are completed. A comprehensive literature search reveals that many researchers have developed models to predict cost overruns by considering only change orders as the main driver of construction cost overrun without considering the MUC impact. Owners and managers, who are in charge of estimating budget and construction duration in both public and private sectors, have limitations in predicting such tasks accurately. Data on completed projects are obtained from one of the nation largest Transit agency for 70 Railroad bridge construction projects. It examines the challenging environment of Railroad Bridge Construction Industry and describes the development of a predictive model of cost deviation in such high-risk projects. Based on an in-depth evaluation and analysis of completed railroad bridge construction projects, historical data was obtained on reasons behind cost overrun and underrun from 25 Railroad bridge projects which experienced cost overrun and underrun as study cases out of 70 completed general Railroad construction projects. This study contributes to a uniquely better understanding of the reasons for cost deviation in Railroad bridge construction projects and provides a decision support tool to quantify the extend of that deviation. Its results are expected to support the bridge owners and contractors who are in charge of estimating budget and construction duration in Railroad Bridge Construction sectors in accurately predicting the construction cost based on adequately calculated cost contingency at the business planning or early stage of a project.

Item Type: Thesis (Doctoral)
Thesis advisor: Williams, T P
Uncontrolled Keywords: construction sector; decision support; duration; private sector; uncertainty; construction cost; construction project; contingency; bridge construction; estimating; road construction; owner
Index terms: owner, deviation, cost overrun, private sector, construction cost, change order, cost deviation, duration, bridge project, road construction, project data, overrun, manager, cost estimating, decision support, bridge construction, agency, construction sector, estimating, construction project
Subjects: production management, infrastructure engineering, practitioner, industry analysis, infrastructure and transport systems, project controls, sociology, decision analysis, contractual condition, civil engineering, financial and cost management, data collection methods
Topics: Time Control, Contract Administration, Cost Management, Business Strategy, Research Practice, Stakeholder Management, Roles and Professions, Engineering Principles, Project Management, Risk Management
Descriptive scope: 4 PCTE

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here