Damoah, I S (2015) An investigation into the causes and effects of project failure in government projects in developing countries: Ghana as a case study. PhD thesis, Liverpool John Moores University, UK.
Abstract
In recent years, project management has become an important part of any organisation and/or government as a result of the changing nature of managing organisations due to technological advancement, and a complex, competitive global marketplace. Projects require huge capital outlay from organisations and/or governments; however, literature indicates that huge sums of money are being lost through project failure and Ghana’s government is no exception to this trend. Therefore, this study investigated the perception of the extent of project failure, causes of project failure and the effects of project failure on key stakeholders of Ghana’s government projects. The purpose of this research is to bridge literature gap(s) in project management and also to provide statistical data that can be used by project management practitioners and policy makers in Ghana and other developing countries. An initial literature review was conducted to development theoretical framework that was used to determine the extent of projects failure, causes and effects of projects failure in Ghanaian government projects. Ten (10) semi-structured interviews (general public (2), contractors (2) and project management practitioners (PMP) (6)) were carried out to evaluate the perception that the participants about the extent of failure, causes and effects of Ghana government projects failure. The data were analysed using content and thematic data analysis techniques. The literature reviewed and the exploratory data identified six (6) project failure criteria that were used to assess the extent of project failure in Ghanaian government projects. Thirty-two (32) and twenty-six (26) possible causes and effects of Ghanaian government project failure were identified respectively. Further data were collected through questionnaire surveys of 265 (contractors=78, PMP=81 and general public=106) participants. The questionnaire data were analysed using statistical techniques which included Descriptive Statistics, Means, Spearman Rank Correlation Coefficients, and Kruskal-Wallis H test of difference in ranks. The findings showed that all the three categories of the study’s participants (contractors, PMP and general public) agreed that Ghanaian government projects fail on all six criteria; however, the extent of failure differs from criterion to criterion. They agreed that the worst performing criterion is meeting the projected time, followed by cost, deliverables, stakeholders' satisfaction, contribution to national development and contribution to the sector where the project is implemented respectively. Secondly, the 32 causes of Ghanaian government projects failure included: monitoring, corruption, political interference, change in government, bureaucracy, fluctuation of prices, lack of continuity, planning, delays in payment, release of funds, change in project leadership, management practices, procurement processes, project funding, commitment to project, selection of project managers, project team formation, project management techniques, feasibility studies, communication, supervision, scope change, capacity, task definition, definition of specification, requirement, regulations, culture and belief systems, user involvement, labour, pressure groups (media, NGOs, political activities etc.), and natural disaster. Further, most of these causes of Ghanaian government projects failure were linked to leadership; however, this was not practitioners but political leadership. The effects identified included: it slows down economic growth, loss of revenue by state, unemployment, bad image for government, collapse of local businesses, cost escalation, government sector underdevelopment, loss of foreign aid/grants, discourages investment, stricter donor regulations, loss of election, financial institutions lose confidence in the state, loss of revenue by the citizens, lack of capacity, sub-standard infrastructure, it slow down citizens' human empowerment, loss of worker hours, pollution, armed robbery and theft, relocation of services, denial of citizens' basic rights, loss of properties, emotional stress on citizens, accidents and deaths, imprisonment, and abandonment of homes. The study revealed that some of these effects are direct whilst others are indirect. Thus, the findings show that the effects are interrelated and sequential – one effect could lead to another effect and in that order. Moreover, the causes and effects were not of equal importance; however, there was a high degree of agreement between the three categories of the study’s participants on the most important causes and effects of failure in Ghanaian government projects.
| Item Type: | Thesis (Doctoral) |
|---|---|
| Thesis advisor: | Mouzughi, Y; Akwei, C A and Zhang, L |
| Uncontrolled Keywords: | communication; corruption; developing countries; employment; feasibility studies; funding; Ghana; government; economic growth; infrastructure; interview; investment; leadership; natural disaster; payment; policy; pollution; procurement |
| Index terms: | feasibility study, economic growth, monitoring, project failure, unemployment, data analysis, funding, project team, developing country, questionnaire, foreign aid, specification, investigation, scope change, statistics, cost escalation, supervision, natural disaster, corruption, employment, pollution, satisfaction, government project, commitment, media, project management, abandonment, relocation, project management technique, procurement process, management practice, interview, survey, practitioner, case study, donor, theft, regulation, empowerment, project manager, Ghana, literature review, revenue |
| Subjects: | completion, design stages, market analysis, economic development, sociology, economic analysis, practitioner, political science, project delivery, control systems, professional ethics, environmental health, contractual condition, administrative law, data analysis and analytics, economic concepts, Geography, economics, project completion, mathematical modelling, psychology, operations management, environmental hazards, data collection methods, criminal law, profession, scope management, project management theory and practice, development economics, contractual arrangements, management |
| Topics: | Legal Issues, Research Practice, Design Practice, Project Management, Sustainability, Stakeholder Management, Procurement, International Construction, Site Management, Geographical Context, Cost Management, Governance, Roles and Professions, Human Resources, Contract Administration, Organizational Design, Business Strategy |
| Descriptive scope: | 4 PCEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here