Pre-design methodology for establishing scope-budget and scope-duration alignment for capital projects

Holmlin, R M (2016) Pre-design methodology for establishing scope-budget and scope-duration alignment for capital projects. PhD thesis, George Washington University, USA.

Abstract

It is well established that projects do not meet their cost, schedule and scope objectives and often fail to deliver the benefits that were hoped for. Part of the challenge is that at the conceptual/pre-design stage, the level of scope definition is often only 1-2% and the resulting pre-design cost estimates typically have an accuracy range of -50% to +100%. Project teams may not feel confident providing this information to the designers as design-to-cost targets and overall project cost management suffers as a result. The proposed methodology was developed to assist with pre-design estimating on a new student health center at a college in the mid-Atlantic region of the United States. Development of a preliminary work breakdown structure allowed development of a cost model targeted at the major cost elements of a capital project by removing cost elements such as sitework and general conditions that have greater variability that is often concealed in cost/SF historical data used for modeling. The regression equation developed, based on five data points of comparable projects ranging in size from 20,000SF to 72,714 SF , with a zero intercept, has an R2 of 0. 9925, a P Value <0. 0001 and a F test score of 661. 63. 63. Using the model to validate the cost of the comparable projects resulted in a cost forecast range of -10. 3% to + 39. 4% as compared to industry standard expected cost range in the pre-design period of -50% to+100%. Using the forecast cost and Bromilow equations to forecast project duration resulted in duration forecasts within approximately +/-18% of the contracted durations. The need for vigorous cost management over the life of a project remains, but this methodology offers an approach to (1) develop design-to-cost targets and (2) for the project team to have greater confidence they have scope-budget and scope-duration matches as the project enters design.

Item Type: Thesis (Doctoral)
Thesis advisor: Sarkani, S and Mazzuchi, T
Uncontrolled Keywords: accuracy; duration; project team; cost management; design cost; estimating; project cost; designer; United States
Index terms: estimating, design stage, cost model, methodology, accuracy, project cost, United States, variability, project team, modelling, estimate, duration, capital project, cost management, designer, design cost
Subjects: professional practice, analytical methods, strategic project management, Geography, research methods, accounting and finance, profession, financial and cost management, project delivery, professional development, economics, statistical analysis, project controls
Topics: Cost Management, Information Management, Research Practice, Roles and Professions, Design Practice, Time Control, Engineering Principles, Geographical Context, Project Management
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here