Development of building information models (BIM) to support innovative time management and delay analysis

Gibbs, D-J (2017) Development of building information models (BIM) to support innovative time management and delay analysis. EngD thesis, Loughborough University, UK.

Abstract

Although time is a critical factor for most projects, the majority of construction projects encounter delay. Conventional methods for managing time tend to use static medium, which can make understanding delay challenging. This can result in reactive management, which contributes to inappropriate mitigation measures, untimely and insufficient claims, and failures to award extensions of time. These consequences are common causes of dispute, which have a negative effect on the construction industry. The likelihood and severity of disputes on construction projects are increasing but it is suggested that building information modelling (BIM) has the potential to reduce the number of delays and disputes in the industry. However, literature directly addressing how to achieve this appears limited. To contribute research to this knowledge gap, this EngD aims to improve the understanding of delay on construction projects through BIM. This is addressed through five objectives, which gather data through a case study, workshop, simulation, questionnaire, focus group, content analysis and the available literature. The findings of each objective contribute to the next stage of research and led to the proposed interactive exhibit, which integrates VARK modes of presentation with 4D modelling technology developed to support BIM. The rationale behind this proposal is supported by five journal publications, which are appended to this document.

Item Type: Thesis (Doctoral)
Uncontrolled Keywords: building information modelling; case study; content analysis; delay modelling; dispute resolution; focus group; questionnaire survey; time management
Index terms: survey, journal, 4D modelling, content analysis, focus group, proposal, publication, delay analysis, mitigation, questionnaire, construction project, critical factor, dispute, case study, workshop, time management, building information modelling, construction industry, modelling, resolution
Subjects: production management, financial risk, digital design, research dissemination and communication, construction type, project planning, analytical methods, industry analysis, information systems, project controls, conflict resolution, dispute resolution, data collection methods, risk assessment, data analysis and analytics
Topics: Cost Management, Information Management, Research Practice, Stakeholder Management, Construction Technology, Digital Applications, Time Control, Engineering Principles, Project Management, Risk Management, Legal Issues
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here