Aljohani, A (2019) Cost overrun causality model in Saudi Arabian public sector construction projects. PhD thesis, Robert Gordon University, UK.
Abstract
Construction performance in Saudi public projects has been poor over the years, with 70% of projects considered as failures and costing the country over 1 trillion SAR (over £202 billion) between 2005 and 2015. The project delivery mechanism used to deliver construction projects is one of the main reasons for such poor performance, as all service providers (consultant, designer, and contractor) are chosen based on the lowest price. The contract evaluation shows that contractors hold most of a project's risks and suffer a cost overrun problem, thereby positioning them as the weakest link in the procurement chain. This study aims to develop a contractor's cost overrun causality model in the Saudi public sector. A systematic literature review was performed and revealed three schools of thought regarding the investigation and identification of cost overrun causes. However, none of the three schools has addressed the limitations of exploring the interaction between any causes identified and then linking root causes with a direct cause, nor including the effects of the context and the process that are used to develop construction projects. Exploring the interaction between causes is important, because the construction projects covered within the literature involved different stakeholders at different phases in a project's lifecycle. Moreover, it has been found that the amount and the causes of cost overrun are different based on the project's location. After the systematic literature review, this study aimed to develop a contractors' cost overrun causality model in the Saudi public sector, which would consider the effects of context, practices and processes of developing construction projects. Specifically, the research explored the commercial context of Saudi public construction project procurement under four major portfolios (economy, business, resources and regulation). Additionally, the research explored the processes and practices that are used to develop construction projects in the sector, based on the Porter model (diamond) and institutional theory. This thesis establishes the link between the commercial context and contractors' performance. Based on the systematic literature review and interviews, the causalities of cost overrun in Saudi Arabian construction projects were critically reviewed, established, classified and evaluated. The data created a causes pool, with over 200 causes - these were then filtered through various means, resulting in 49 remaining causes. The study explores the relationship between these causes in order to create causal paths and, eventually, the overall model. The model-building process and the resultant outputs were reviewed by two industry experts, resulting in further refinement and simplification of the model. The final model contains 49 causal chains that have each been thoroughly explained. The nature of the problem investigated required this research to adopt a pragmatic and abductive approach in order to achieve its objectives. The main methodologies used were systematic literature review, case study, interviews, and project documentation. The research emphasises the importance of investigating the context and project-development process. In fact, by comparing Saudi public sector practices to established best practices, the study found that causal chains were triggered and contributed to by weaknesses within the context, process, and practices, which occur in the early stage of a project's lifecycle. However, it is established that only direct causes occur during the construction phase. Moreover, the results confirm that the current environment, regulation, practices, and behaviours of the Saudi public sector increase the risks of projects failing and damaging the construction industry. Therefore, based on the findings of the research, this thesis recommends that the Saudi public agency should: 1) adopt a project delivery approach that reduces the fragmentation in delivering a construction project, and which is tailored to the project context and characteristics; 2) adopt a new method to finance construction projects that is less affected by fluctuations in the oil economy; 3) build a long-term relationship with service providers (designers, consultants, and contractors) that is built on trust, sharing of information, and lesson learning and improvement; 4) adopt a new contract that is based on fair risk appropriation, where the risk transfer is to the most suitable party to effectively manage that risk; 5) generate general regulations and laws that transform the construction industry so as to be less affected by the external environment, more controlled by all the involved parties, and in which it becomes more attractive to invest.
| Item Type: | Thesis (Doctoral) |
|---|---|
| Thesis advisor: | Moore, D and Omotayo, T |
| Uncontrolled Keywords: | case study; documentation; interview; procurement; public sector; regulation; Saudi Arabia; schools; stakeholders |
| Index terms: | public sector, fragmentation, methodology, interaction, agency, cost overrun, investigation, lifecycle, costing, project documentation, public project, Saudi Arabia, case study, simplification, project procurement, construction phase, institutional theory, interview, abductive approach, project delivery, building process, best practice, regulation, construction project, construction performance, documentation, construction industry, public construction, systematic literature review, designer |
| Subjects: | industry analysis, production management, research evaluation and metrics, infrastructure engineering, behavioral psychology, data collection methods, accounting and finance, administrative law, sociology, project planning, profession, management, performance assessment, financial and cost management, contractual arrangements, Geography, research methods, building construction, project delivery, research design and methodology, political science, business, professional development |
| Topics: | Project Management, Research Practice, Organizational Design, Cost Management, Roles and Professions, Legal Issues, Engineering Principles, Business Strategy, Geographical Context, Procurement, Site Management, Information Management, Governance |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here