Duration estimators and productivity metrics for highway construction

Nevett Fernández, G (2020) Duration estimators and productivity metrics for highway construction. PhD thesis, University of Colorado at Boulder, USA.

Abstract

Estimating durations of projects is an ongoing challenge for owners and contractors in the transportation construction industry. This challenge can be related to difficulties in measuring productivity. The current dissertation studied the influence that construction (bid) quantities and project characteristics have on the duration of transportation construction projects, and also developed a new metric to understand the historical trends of productivity. The author collected historical data of 1,500 transportation construction projects executed between 2004 and 2017. These data were used to conduct a quantitative analysis of how construction quantities and project characteristics can be used to predict project durations. Additionally, the data collected were used to develop a new metric to assess the overall productivity trends at a project-type level. Historically, there are three well know methods for duration estimation in transportation construction: Bar (Gantt) Charts, Critical Path Method, and Estimated Cost Method. The latter being a method that uses a relationship between the cost and the duration of a project. This dissertation used Multiple Linear Regression and Artificial Neural Networks to analyze the relationships that project quantities and characteristics have with the duration of projects. Findings from this dissertation suggest that the cost of a project is not important to estimate the duration of a project when analyzed alongside project quantities and characteristics contrary to what is suggested by the Estimated Cost Method. Additional findings from this dissertation suggest that the productivity of the overall transportation construction industry did not show statistically significant signs of change over the period analyzed when measured with the metric developed during this dissertation. Nonetheless, the productivity of construction of Bridge projects did show an increasing trend over the period described. The current dissertation has practical implications for the estimation of the duration of transportation construction projects, as well as theoretical contributions to the ongoing debate about the trend of productivity in the transportation construction industry.

Item Type: Thesis (Doctoral)
Thesis advisor: Goodrum, P M
Uncontrolled Keywords: duration; construction project; highway; artificial neural network; critical path method; estimating; productivity; estimator; owner; neural network; quantitative analysis
Index terms: artificial neural network, neural network, estimator, construction project, estimating, critical path method, quantitative analysis, estimation, productivity, owner, highway construction, duration, construction industry, bridge project, estimate, dissertation
Subjects: production management, operations research, research dissemination and communication, sociology, project controls, industry analysis, infrastructure and transport systems, civil engineering, management, modelling and simulation, financial and cost management, data analysis and analytics, artificial intelligence, profession
Topics: Engineering Principles, Project Management, Roles and Professions, Stakeholder Management, Research Practice, Cost Management, Business Strategy, Time Control, Digital Applications
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here