The role of project delivery methods on the execution of construction projects in the Kenyan judiciary

Okello, J F; Bowa, O and Migosi, J (2025) The role of project delivery methods on the execution of construction projects in the Kenyan judiciary. Construction Economics and Building, 25(1), pp. 49-68. ISSN 2204-9029

Abstract

The Kenyan Judiciary's construction industry experienced a significant upturn with 63 major court projects funded by the World Bank and Kenya Government from 2012 to 2021. However, these projects faced delays and scope changes, affecting performance indicators like time, cost, site dispute, and quality. The study hypothesized that project delivery methods have no significant influence on the execution of court-building projects in relation to time, cost, site disputes, and quality. Reliability was tested using Cronbach's alpha technique, and validity was tested using principal component analysis (PCA). This study combined the collection and analysis of quantitative and qualitative data using a mixed-methods approach. Sixty-three projects were surveyed using a convergent parallel mixed-survey design. Document analysis was used to obtain secondary data, and questionnaires and interview guides were used to collect the primary data. Correlation and regression analysis techniques were used for inferential statistical analysis. The slope coefficients were considered significant at p ≤ 0.05. Thematic and document analyses were applied to the qualitative data to triangulate the findings with the quantitative data. According to the study, project delivery methods significantly influenced the execution of construction projects in terms of quality, cost, and site disputes, but not time. The study further highlights the need for flexible, context-specific project delivery approaches in the Kenyan Judiciary to ensure timely completion of court-building infrastructure.This research offers helpful information concerning the use of appropriate delivery methods to scholars, practitioners of project and construction management, policymakers, and other parties involved in implementing the Kenyan Judiciary's court-building infrastructure.

Item Type: Article
Uncontrolled Keywords: execution of construction projects; Kenyan judiciary; mixed-methods research; performance metrics; project delivery methods; questionnaire survey
Index terms: survey, slope, judiciary, performance indicator, scope change, interview, performance metric, Kenya, practitioner, questionnaire, construction project, validity, statistical analysis, World Bank, secondary data, document analysis, delivery method, dispute, project delivery, regression analysis, construction industry, principal component analysis
Subjects: performance measurement, performance management, delivery method, geotechnical engineering, industry analysis, statistical analysis, data collection methods, dispute resolution, data science, institutional frameworks, project delivery, production management, Geography, evaluation and assessment methods, practitioner, scope management, legal systems
Topics: Legal Issues, Quality Management, Procurement, Geographical Context, Project Management, Engineering Principles, Roles and Professions, Governance, Research Practice
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here