Influence of macroeconomic factors on construction costs: An analysis of project cases

Castelblanco, G; Fenoaltea, E M; De Marco, A and Chiaia, B (2025) Influence of macroeconomic factors on construction costs: An analysis of project cases. Construction Management and Economics, 43(3), pp. 196-212. ISSN 0144-6193

Abstract

This study explores the relationship between price increase and project cost increase under macroeconomic shocks by considering the hierarchical structure within price categories, diversification of the cost breakdown structure, infrastructure sector, delivery system, construction methods, and type of bid. The analysis of a large construction company with five large projects as embedded units of analysis reveals significant variations in the relative influence of specific factors across the projects. Unit price categories located higher in the hierarchical breakdown structure display lower vulnerability to macroeconomic changes due to their unique and group-specific influencing factors while price categories influenced by macroeconomic factors depart at lower values in the hierarchical structure. Projects with low-cost breakdown structure diversification can either mitigate or exacerbate cost increases depending on construction methods (off-site or on-site), price drivers of most representative materials (global or local), and delivery systems risk allocation. Under macroeconomic crisis periods, public entities may consider giving high priority to projects more reliant on materials driven by regional dynamics (e.g., concrete pouring) over those driven by global market conditions (e.g., steel, aluminum) while prioritizing integrated delivery systems (e.g., design-build) that promote enhanced collaboration, proactive risk management, aligned incentives, and adaptability for managing complexities and volatilities. Complementary, for projects with higher reliance on global market-driven materials, the results suggest that contractors should prioritize early procurement and acquisition of highly volatile resources in projects under macroeconomic crises.

Item Type: Article
Uncontrolled Keywords: integrated management; public-private partnership; risk management; risk propagation; social network analysis; stakeholder management
Index terms: diversification, dynamics, propagation, risk allocation, risk management, influencing factor, prioritizing, construction cost, partnership, acquisition, cost increase, variation, collaboration, adaptability, vulnerability, stakeholder management, infrastructure sector, complexity, social network analysis, market condition, project cost, construction company, construction method
Subjects: financial and cost management, participation process, engineering process, business, risk assessment, economic and policy analysis, decision analysis, partnership management, systems engineering, industry analysis, economics, management, contractual condition, organization, user focus, building construction, market analysis, environmental hazards, research methods, financial risk
Topics: Engineering Principles, Sustainability, Risk Management, Research Practice, Business Strategy, Cost Management, Stakeholder Management, Design Practice, Organizational Design, Site Management, Contract Administration
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here