Salhab, D; Lindhard, S M and Hamzeh, F (2024) Schedule compression and emerging waste in construction: An assessment of overlapping activities. Engineering, Construction and Architectural Management, 31(12), pp. 4920-4941. ISSN 0969-9988
Abstract
Purpose: Compressing the schedule by using overlapping activities is a commonly adopted approach for accelerating projects. However, this approach might channel a variety of risks into the construction processes. Risks imply waste; still, evaluating the effects of using overlapping activities on schedule quality has been a looming gap in construction research. Therefore, this paper aims to study the quality of overlapping in terms of emerging waste and to demarcate the boundaries of the overlapping envelope. Design/methodology/approach: This study presents a method for assessing the consequences of implementing overlapping activities in a schedule on two types of waste namely waiting time and variation gap. A critical path method (CPM) network including eleven activities is modeled stochastically where the durations of individual activities are sampled as beta-distributions. Using program evaluation and review technique (PERT) assumptions to calculate the schedule dates, the network is simulated for various amounts of overlapping and the corresponding waste is quantified each time. Findings: Results show that not only the returns on overlapping are diminishing after a certain overlap percentage, but also waste in the production system increases. Particularly, results reveal that compressing the schedule leads to a decrease in variation gaps, but at the same time, it leads to a larger increase in waiting times, which creates more waste. Originality/value: The presented study shows through simulation how overlapping activities affects productivity by identifying wastes. It shows that despite the apparent gains, overlaps should be used with caution, and while considering the side-effects of increased waste which introduces a need for increased managerial awareness.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | overlapping activities; schedule compressing; scheduling; simulation; waste |
| Index terms: | scheduling, production system, methodology, construction process, variation, boundaries, critical path method, schedule compression, programme evaluation and review technique, productivity, duration |
| Subjects: | management, contractual condition, project controls, manufacturing engineering, research methods, building construction, operations research, property law |
| Topics: | Business Strategy, Research Practice, Site Management, Time Control, Contract Administration, Engineering Principles, Legal Issues |
| Descriptive scope: | 3 PCT |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here