S-curve adjustment approaches for a force majeure event: COVID-19 as an example

Yang, J B and Chen, Y F (2025) S-curve adjustment approaches for a force majeure event: COVID-19 as an example. Engineering, Construction and Architectural Management, 32(3), pp. 1621-1642. ISSN 0969-9988

Abstract

Purpose: An S-curve is an essential project-management tool. However, it is difficult to adjust S-curve to deal with a force majeure event. The present study develops four valuable adjustment approaches, designed to achieve a compromise between the views of the client and contractor. These can be used to control projects after a force majeure event. Design/methodology/approach: The present study develops four adjustment approaches, which can be used to achieve a compromise between the views of the client and those of the contractor when controlling projects after a force majeure. To determine the S-curves during a force majeure event, two approaches can be selected: BCWS (budgeted cost of scheduled work)-base approach, or BCWP (budgeted cost of work performed)-base approach. To determine the rest of S-curves after a force majeure event, two approaches can be considered: maintaining the original curve of the remaining BCWS, or allocating the original curve of the remaining BCWS. Based on the validation of three empirical cases, drawn from a professional project-management website, this study confirms the feasibility of four proposed empirical approaches and a selection procedure for S-curve adjustment. Findings: The S-curve-adjustment approaches presented here can be used to deal with cases that are ahead of, on and behind schedule. Using the proposed approaches and selection procedure, contractors can easily revise S-curves and control projects more effectively. To deal with a force majeure event, such as COVID-19, they are strongly advised to adopt the approaches labeled SA-A1 (to adjust the S-curve based on the extension ratio multiplied by the difference in progress during the force majeure) and SA-B1 (to maintain the original curve of the remaining BCWS) for the A/E and E/F curves, respectively. Research limitations/implications: The proposed approaches can be used in cases of continuous construction during force majeure events. If construction work is totally suspended during such an event, it will be necessary to fine-tune the proposed approaches. Originality/value: Previous studies have used case-oriented or mathematical-simulation approaches to forecast S-curves. The present study proposes simple approaches that allow the client and contractor to adjust the S-curve easily after a force majeure event. These approaches can be used to adjust work and project-completion targets within an extended duration. Selecting the right S-curve adjustment approach can help to control the remainder of the project, reducing the possibility of delay claims.

Item Type: Article
Uncontrolled Keywords: COVID-19; force majeure; project control; s-curve; scheduling
Index terms: scheduling, COVID-19, validation, methodology, force majeure, project control, duration, construction work, s-curve
Subjects: control systems, project controls, professional development, health risk and incident analysis, economics, operations research, operations management, mitigation, research methods
Topics: Time Control, Contract Administration, Research Practice, Information Management, Cost Management, Project Management, Health and Safety
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here