An investigation of the factors influencing the success of construction planning for the 2012 olympic stadium: An ethnographic study

Subbiah, A (2012) An investigation of the factors influencing the success of construction planning for the 2012 olympic stadium: An ethnographic study. In: Smith, S D (ed.) Proceedings of 28th Annual ARCOM Conference, 3-5 September 2012, Edinburgh, UK.

Abstract

Adherence to the planned duration is one of the main criteria when judging whether a construction project is a failure or not. In addition, construction planning is said to be successful if the project completes within the planned duration; or if it identifies an issue well in advance, thereby alerting the project management team to solve the issue before it causes any impact on the completion date. This research investigates the factors that influenced the success of construction planning of 2012 London Olympic Stadium. An approach of participant observation was adopted which is informed by the principles of ethnography: one that reports the participants' view of their world rather than imposing an artificial theoretical framework upon it. As a senior planning engineer working professionally on the Olympic Stadium from pre-construction until final completion, key human-relations factors were observed and identified that had an impact on the management and execution of the construction planning. The success factors were identified and relate to, for example: the effectiveness of preconstruction planning; the inclination of top organization hierarchy towards construction planning; the inter relationship between the project participants; the influence of the client and contract; and the efficiency of planning team. It was found that a 'shadow culture' exists between the project participants which, it is argued, is only observable from the perspective of an embedded participant observer. This shadow culture acts to enable the management of the planning process and its efficacy relates to the 'quality' of human inter-relationships in the planning team and among immediate stakeholders. The research concludes by questioning the myth among project participants that construction planning is a mechanistic process that has to be conducted solely by the planning team.

Item Type: Conference Paper (Paper)
Uncontrolled Keywords: construction planning; inter relationship; participant observant; shadow process
Index terms: pre-construction, construction planning, project management team, engineer, efficiency, duration, investigation, ethnography, effectiveness, observation, success factor, planning process, construction project, London
Subjects: construction planning, qualitative and interpretive research, project controls, Geography, profession, data collection methods, health monitoring assessment and metrics, project delivery, performance management, production management
Topics: Health and Safety, Project Management, Geographical Context, Site Management, Quality Management, Time Control, Research Practice, Roles and Professions
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here