A neuro-fuzzy hybrid model for predicting final cost of water infrastructure projects

Ahiaga-Dagbui D D, T O and Smith S D, W S (2013) A neuro-fuzzy hybrid model for predicting final cost of water infrastructure projects. In: Smith, S D and Ahiaga-Dagbui, D D (eds.) Proceedings of 29th Annual ARCOM Conference, 2-4 September 2013, Reading, UK.

Abstract

Nine out of ten infrastructure projects exceed their initial cost estimates. Accuracy of construction cost estimates remains a contentious area of debate within both academia and industry. Explanations for this have ranged from scope changes, risk and uncertainty, optimism bias, technical and managerial difficulties, suspicions of corruption, lying and insufficient required information for accurate estimation. The capacity for tolerance and imprecise knowledge representation of fuzzy set theory is combined with the learning and generalising capabilities of neural networks to develop neuro-fuzzy hybrid cost models in this paper to predict likely final cost of water infrastructure projects. The will help to increase reliability, flexibility and accuracy of initial cost estimates. Neural networks is first used to develop relative numerical weightings of cost predictors extracted from primary data collected on 98 completed projects. These were then standardised into fuzzy sets to establish a consistent framework for combining the effect of each variable on the overall final cost. A three-point fuzzy lower, upper and mean estimate of likely final cost is generated to provide a tolerance range for final cost rather than the traditional single point estimate. The performance of the final models ranged from 3.3% underestimation to 1.6 % overestimation. The best models however averaged an error of 0.6% underestimation and 0.8% overestimation of final cost of the project. The results are now being extended to a larger database of about 4500 projects in collaboration with an industry partner.

Item Type: Conference Paper (Paper)
Uncontrolled Keywords: artificial neural network; cost estimation; cost modelling; cost overrun; fuzzy set theory
Index terms: estimate, cost overrun, estimation, modelling, academia, cost model, optimism bias, corruption, database, scope change, artificial neural network, cost estimating, construction cost, accuracy, infrastructure project, neural network, cost estimate, fuzzy set, fuzzy set theory, collaboration
Subjects: decision-making and optimization, artificial intelligence, analytical methods, cognitive psychology, professional ethics, educational institutions, modelling and simulation, financial and cost management, professional development, data management, management, infrastructure and transport systems, scope management
Topics: Information Management, Cost Management, Organizational Design, Legal Issues, Research Practice, Engineering Principles, Education, Digital Applications, Project Management
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here