Abubaker, A E (2010) Improvement of project planning in Libya. PhD thesis, University of Newcastle upon Tyne, UK.
Abstract
Delays in many construction projects are a global phenomenon and the construction industry in Libya is no exception. Scheduling problems result in late completion. This thesis reviews project planning with specific reference to Libya, to identify and trial new approaches. Although there are many infrastructure projects in Libya, few studies have been made. Further, earlier studies considered the causes and effects of project delays, whereas this thesis focuses on improvement of planning in the Libyan context. A mixed-method data gathering procedure using face-to-face interviews and case studies was used. A survey by questionnaire was conducted to discover whether traditional methods, computer techniques or risk simulations were normally used to set time targets. Six case studies were selected, where the contractors had actually developed project plans using conventional methods (e. g. Bar Charts, CPM, PERT). A review of the literature identified conventional and novel approaches to planning in particular the Last Planner approach. A trial of the Last Planner System (LPS) was conducted in Libya. Four case studies were reviewed, two as a ‘control group’ for data collection on time performance. The other case studies were the experimental group. The Last Planner System was presented at a seminar to their project managers and planners who were then asked to apply LPS and monitor results using documentation provided by the researcher. The unexpected results found some projects finished on time, but the actual time spent was much lower than planned. The planners appeared to be building anticipation of delay into the project plans, the common causes of delay being identified in the questionnaire results. The thesis then proposes an improved planning process, based on the application of last planner system.
| Item Type: | Thesis (Doctoral) |
|---|---|
| Uncontrolled Keywords: | Libya; case studies; documentation; project planning; scheduling |
| Index terms: | project planning, Libya, project delay, questionnaire, construction project, last planner system, time performance, documentation, survey, face, scheduling, interview, infrastructure project, construction industry, planner, causes of delay, case study, project manager, planning process |
| Subjects: | professional development, project controls, industry analysis, infrastructure and transport systems, profession, data collection methods, control systems, Geography, production management, operations research, psychology |
| Topics: | Research Practice, Information Management, Roles and Professions, Organizational Design, Time Control, Project Management, Geographical Context, Engineering Principles |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here