Tied supply chains in construction projects: Lessons from London underground's public-private-partnership

Gannon M, M S A J (2013) Tied supply chains in construction projects: Lessons from London underground's public-private-partnership. In: Smith, S D and Ahiaga-Dagbui, D D (eds.) Proceedings of 29th Annual ARCOM Conference, 2-4 September 2013, Reading, UK.

Abstract

This paper addresses the lessons learnt by London Underground (LU), the public sector contracting authority, when a tied supply chain arrangement, namely where shareholders are also commercial beneficiaries from sub-contracted delivery, was utilised by a consortium to upgrade its system under an innovative Public-Private-Partnership (PPP) model. Research on tied supply chains and their application in PPP agreements is significantly under reported. The paper sets out insights from industry using secondary sources, which include parliamentary reports and reviews. The paper postulates that different models of tied supply chains might exist, from those that rely on some form of equity structure to those that rely only on the collective reputation of the supply network. Five lessons learnt from the contracting authority’s perspective are highlighted on the use of tied supply chains in PPP contractual arrangements. Whilst tied supply chains can be effective, they are better utilised in PPP contractual arrangements where there is certainty with the scope of works and required resources. During the bid evaluation stage the contracting authority must evaluate whether prospective bidding consortiums have satisfactory governance arrangements at Board level and across its tied supply chain. Furthermore, the contracting authority must include governance safeguards within the contractual documents and strictly regulate the tied supply chain to prevent failure. This paper provides a new insight into tied supply chains and their governance with respect to Public-Private-Partnership models, and other forms of procurement.

Item Type: Conference Paper (Paper)
Uncontrolled Keywords: governance; procurement; public-private partnership; tied supply chain
Index terms: safeguards, consortium, governance, partnership, public sector, bid evaluation, London, construction project, documents, agreements, bidding
Subjects: contract formation, bidding, business, occupational health and safety management, partnership management, administrative law, tendering, professional development, Geography, production management
Topics: Geographical Context, Project Management, Information Management, Health and Safety, Procurement, Governance, Stakeholder Management, Legal Issues, Contract Administration
Descriptive scope: 2 PC

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here