Ismail, M Z; Mohamad Ramly, Z; Darmansah, N F and Misnan, M S (2025) Rail construction cost risk management with bow-tie analysis: Contractor’s perspective. Built Environment Project and Asset Management, 15(4), pp. 753-771. ISSN 2044-124X
Abstract
This study aims to examine the risks of cost overrun in rail construction from the contractor’s perspective. A three-phase approach is proposed (initial, planning and execution) to enhance comprehension of risk management optimization. Data collection involved distributing questionnaires to rail construction cost management professionals. The instrument was built by identifying key themes, concepts and findings from literature and pilot surveys. Data analysis consists of integrating the findings into a Probability Impact Matrix (PIM) and bow-tie diagrams based on probability and impact assessments. The diagrams created detailed risk mitigation tables and simplified response planning. Initial data analysis showed 36 factors causing cost overruns in 3 phases of rail construction. The responses were analysed by probability and impact, forming a risk matrix, which was then translated into a bow-tie diagram. The information was then incorporated into the PIM that assists in determining appropriate risk responses based on risk levels. The index values ranged from moderate to very high. The execution phase exhibited the highest impact, particularly with risks associated with incompetent work schedule management and overdependence on specialist works, indicating a need for proactive risk mitigation strategies. This research indicates that the execution phase poses significant risks to rail cost performance, particularly in schedule and sub-contractor management. While contractors bear significant responsibility during this phase, government must be active in mitigating cost-related risks. Additionally, individual experience is crucial as contractors, clients and consultants are recommended to be adequately experienced to ensure a seamless process, minimal errors and effectively address multiple risks in the rail construction.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | bow-tie analysis; cost management; rail construction; risk management |
| Index terms: | data analysis, risk response, survey, strategy, questionnaire, sub-contractor, impact assessment, cost performance, risk mitigation, cost management, construction cost, cost overrun, risk management |
| Subjects: | economics, management, financial and cost management, data analysis and analytics, value management, risk assessment, data collection methods, financial risk, accounting and finance, practitioner |
| Topics: | Project Management, Risk Management, Research Practice, Business Strategy, Cost Management, Roles and Professions |
| Descriptive scope: | 4 PCEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here