Unveiling factors influencing the duration of arbitration practice in the Tanzania construction industry

Luvara, V G M and Benjamin, M (2025) Unveiling factors influencing the duration of arbitration practice in the Tanzania construction industry. International Journal of Building Pathology and Adaptation, 43(6), pp. 1612-1633. ISSN 2398-4708

Abstract

Most construction projects are undertaken with the incentive of some form of profit which in business attracts disputes that key disputing parties intend to resolve through mechanisms such as arbitration as early as possible so that they may advance with other activities associated with the project. However, this intention is regularly unfulfilled, disappointing the parties with late arbitration resolution. This study, therefore, explored the duration influencing factors (DIFs) facing arbitration practice in the Tanzania construction industry. A concurrent convergence mixed methods approach was used where a total of 12 DIFs were identified from the literature, and data were then collected from 39 construction arbitrators, 8 semi-structured interviews and 4 documentary reviews. Descriptive and inferential statistics were employed for quantitative data and directed content analysis for the qualitative data. Results show that contrary to most people's convictions, delays in arbitration are regularly caused by the disputing parties rather than the arbitrating party or the authority. The study identified cooperation amongst the tribunal parties, poor accuracy and submission of documents and material evidences, late payment of arbitration fees, and skills, experience, reputation and profession of the arbitrator to be the most critical factors that cause late arbitration resolution. The use of mixed methods concurrent triangulation convergence approach provides a unique contribution to knowledge by highlighting how the efficacy of arbitration in time performance could be further developed through understanding the critical factors that drive the proceedings duration in the Tanzania construction industry.

Item Type: Article
Uncontrolled Keywords: arbitration; conflicts; construction disputes; duration influencing factors; Tanzania
Index terms: construction project, time performance, evidence, documents, cooperation, triangulation, interview, content analysis, profit, accuracy, profession, statistics, arbitrator, resolution, late payment, duration, construction industry, arbitration, construction dispute, influencing factor, mixed method, tribunal, Tanzania, dispute, critical factor
Subjects: conflict resolution, project controls, payment, industry analysis, professional development, data analysis and analytics, profession, risk assessment, data collection methods, research design and methodology, mathematical modelling, dispute resolution, Geography, production management, psychology, economic analysis, evaluation and assessment methods, institututions
Topics: Geographical Context, Project Management, Risk Management, Legal Issues, Business Strategy, Information Management, Research Practice, Roles and Professions, Stakeholder Management, Contract Administration, Time Control, Organizational Design
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here