Supervised learning to covering cost risk through post-construction evaluation of transportation projects by project delivery methods

Bae, J (2025) Supervised learning to covering cost risk through post-construction evaluation of transportation projects by project delivery methods. Engineering, Construction and Architectural Management, 32(9), pp. 5863-5884. ISSN 0969-9988

Abstract

Purpose - The main objectives of this study are to (1) develop and test a cost contingency learning model that can generalize initially estimated contingency amounts by analyzing back the multiple project changes experienced and (2) uncover the hidden link of the learning networks using a curve-fitting technique for the post-construction evaluation of cost contingency amounts to cover cost risk for future projects. Design/methodology/approach - Based on a total of 1,434 datapoints collected from DBB and DB transportation projects, a post-construction cost contingency learning model was developed using feedforward neural networks (FNNs). The developed model generalizes cost contingencies under two different project delivery methods (i.e. DBB and DB). The learning outputs of generalized contingency amounts were curve-fitted with the post-construction schedule and cost information, specifically aiming at uncovering the hidden link of the FNNs. Two different bridge projects completed under DBB and DB were employed as illustrative examples to demonstrate how the proposed modeling framework could be implemented. Findings - With zero or negative values of change growth experienced, it was concluded that cost contingencies were overallocated at the contract stage. On the other hand, with positive values of change growth experienced, it was evaluated that set cost contingencies were insufficient from the post-construction standpoint. Taken together, this study proposed a tangible post-construction evaluation technique that can produce not only the plausible ranges of cost contingencies but also the exact amounts of contingency under DBB and DB contracts. Originality/value - As the first of its kind, the proposed modeling framework provides agency engineers and decision-makers with tangible assessments of cost contingency coupled with experienced risks at the post-construction stage. Use of the proposed model will help them evaluate the allocation of appropriate contingency amounts. If an agency allocates a cost contingency benchmarked from similar projects on aspects of the base estimate and experienced risks, a set contingency can be defended more reliably. The main findings of this study contribute to post-construction cost contingency verification, enabling agency engineers and decision-makers to systematically evaluate set cost contingencies during the post-construction assessment stage and achieving further any enhanced level of confidence for future cost contingency plans.

Item Type: Article
Uncontrolled Keywords: construction planning; decision support systems; methodology; project management
Index terms: evaluation technique, decision support, feedforward, transportation project, neural network, methodology, agency, cost information, engineer, construction cost, bridge project, estimate, modelling, project delivery, construction planning, project management
Subjects: evaluation and assessment methods, analytical methods, research methods, accounting and finance, control systems, profession, project delivery, financial and cost management, construction planning, artificial intelligence, project management theory and practice, infrastructure and transport systems, decision analysis, sociology
Topics: Digital Applications, Site Management, Cost Management, Research Practice, Roles and Professions, Project Management, Engineering Principles, Risk Management, Procurement
Descriptive scope: 4 PCTA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here