Boateng, P; Ahiaga-Dagbui, D; Chen, Z and Ogunlana, S (2015) Modelling economic risks in megaproject construction: A systemic approach. In: Raiden, A and Aboagye-Nimo, E (eds.) Proceedings of 31st Annual ARCOM Conference, 7-9 September 2015, Lincoln, UK.
Abstract
Megaprojects present significant economic risks to their financiers and sponsors. Factors such as inflation, cash flow issues, material and energy price hikes and change in government policies can cause such capital intensive projects to overrun planned budget and schedule allocations. Where the project is a commercial asset, delayed completion time and cost overruns usually have significant impact on the profitability of the project as well as the estimated returns on investment over the operational phase of the project. Understanding the dynamics of specific risks can thus be very crucial in designing containment measures to deal with their likely impact on the project. Using a case-study of the Edinburgh Trams project in Scotland, the dynamics of identified economic risks in transportation megaprojects is presented. Through the combination of interviews, questionnaires and non-participant observation, different economic risk factors were first identified. The identified factors were then prioritised using Analytical Network Process (ANP) to establish the most salient economic variables on the Tram project. Some of these factors include material and energy price increases as a result of the 2008 recession, as well as inflation and changes in government funding policies. The selected factors from the ANP were then modelled within a System Dynamics (SD) framework to appraise their measured economic impact on the project to gain a fuller understanding of the interrelationships between the variables in the system. The mean impact of economic risks on Edinburgh Trams was estimated to be about 22%.
| Item Type: | Conference Paper (Paper) |
|---|---|
| Uncontrolled Keywords: | analytical network process; cost overrun; economic risk; edinburgh trams; megaproject; system dynamics |
| Index terms: | observation, recession, interview, cash flow, cost overrun, overrun, inflation, funding, dynamics, system dynamics, government policy, completion time, profitability, economic impact, risk factor, Scotland, questionnaire, modelling, megaproject |
| Subjects: | economic analysis, financial and cost management, strategic project management, analytical methods, public policy, computing systems, data collection methods, financial analysis, systems engineering, environmental hazards, project controls, Geography, financial management |
| Topics: | Governance, Sustainability, Business Strategy, Cost Management, Project Management, Geographical Context, Research Practice, Engineering Principles, Time Control, Digital Applications |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here