Supply risk management and timely completion of force account construction projects among local government authorities in dodoma, Tanzania

Mwaiseje, S S; McHopa, A D and Panga, F P (2026) Supply risk management and timely completion of force account construction projects among local government authorities in dodoma, Tanzania. International Journal of Building Pathology and Adaptation, 44(1), pp. 91-109. ISSN 2398-4708

Abstract

Purpose – The study's purpose is to contribute to the supply risk management literature by examining its implications in Tanzania, specifically in the timely completion of force account construction projects in Local Government Authorities (LGAs). Design/methodology/approach – A cross-sectional survey design was employed to gather data from 318 respondents in primary schools within the Dodoma region. A covariance-based structural equation modelling (CB-SEM) structural equation modelling was employed to examine the relationship of the variables. Findings – The study's findings underscore the crucial role of supply risk management, including multi-sourcing, effective supplier selection, post-qualification of suppliers, and effective communication with suppliers in the timely completion of FA construction projects. Notably, effective supplier selection emerges as the most influential factor, significantly contributing to the timely completion of these projects. Research limitations/implications – The study focused on LGAs in Tanzania. It is important to exercise caution when making broad generalizations about the findings. Also, the study was based on a cross sectional survey design; future research could consider a longitudinal design approach. Practical implications – This study offers practical insights for procurement practitioners and members of the Force Account committee in the public sector, offering guidance on how to improve the management of supply risks and, consequently, enhance the timely completion of construction projects. Originality/value – This study stands out in the literature by examining the implications of supply risk management on the timely completion of force account construction projects in Tanzania. It significantly enriches the existing knowledge of supply risk management, particularly in the context of effective supplier selection in public procurement. These insights are of great value to researchers, practitioners, and policymakers in the field.

Item Type: Article
Uncontrolled Keywords: construction projects; force account; procurement; supply risk management; timely completion of projects
Index terms: construction project, methodology, influential factor, practitioner, structural equation modelling, survey, local government, risk management, public sector, exercise, qualification, Tanzania
Subjects: administrative law, statistical analysis, risk assessment, data collection methods, Geography, production management, educational resources, research methods, practitioner, health behaviours and lifestyles
Topics: Roles and Professions, Research Practice, Education, Legal Issues, Risk Management, Project Management, Geographical Context, Health and Safety
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here