A constructability methodology to integrate planning and design for workers' safety in construction management

Alzayd, Rana (2016) A constructability methodology to integrate planning and design for workers' safety in construction management. DrIng thesis, University of Braunschweig & University of Florence, Germany.

Abstract

There are two important reasons for accidents resulting in injuries and fatalities on construction sites, i.e. the interference of different activities and the fact that aspects of workers' safety are considered to be only a concern of the construction phase. The main objective of this research was to incorporate a new workers' safety model into the existing critical path method (CPM) which is used as a supplemented tool in the planning and design phases to identify, remove or minimise the risk of accidents. In a first task the WSiCPM framework (integrating Workers' Safety into CPM) was developed. A matrix in the database was automated to analyse all interfering activities and to evaluate potential hazards. Besides the usual qualitative risk assessment based on expert judgment, the probability of an accident is calculated for each pair of interfering activities using new equations depending on parameters such as overlapping duration, overlapping working area, number of workers and type of hazard. The severity of an accident is estimated analogously to the compensation of casualties by insurance companies and is transformed to a monetary value representing the accident cost. In addition, the framework makes suggestions to eliminate or minimise the risk, e.g. by separating the activities spatially or temporally, modifying the path or re-scheduling the activities. In a second task the concept of 'schedule for safety' was introduced by linking building design for safety (BDS) with CPM. The supplemented BDS can be applied in both the construction and control phases. New safety indicators were derived to assess the level of an accident and the impact on the project cost. The WSiCPM framework can help to overcome existing deficiencies of workers' safety through the link between schedule and design and between temporal and spatial attributes, and by considering the safety issues in all phases of the project. The example application demonstrates that this can lead to significant improvements in health and safety on construction sites.

Item Type: Thesis (Doctoral)
Thesis advisor: Hosser, Dietmar and Capone, Pietro
Uncontrolled Keywords: design; schedule; workers safety; constructability; space-time-conflict; safety indicators
Index terms: judgment, building design, database, design phase, insurance, risk assessment, duration, constructability, compensation, construction phase, fatalities, health and safety, scheduling, injury, project cost, construction site, safety issue, methodology, critical path method
Subjects: architectural design, economic analysis, professional practice, operations research, financial risk, health safety and environment, research methods, project delivery, work location, dispute resolution, health conditions and diseases, data management, project controls, construction integration, economics, health risk and incident analysis
Topics: Business Strategy, Cost Management, Research Practice, Digital Applications, Design Practice, Time Control, Site Management, Health and Safety, Project Management, Legal Issues
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here