Appropriate delay analysis techniques to analyse delays in road construction projects in Sri Lanka

Ekanayake, E M K and Perera, B A K S (2016) Appropriate delay analysis techniques to analyse delays in road construction projects in Sri Lanka. Built Environment Project and Asset Management, 6(5), pp. 521-534. ISSN 2044-124X

Abstract

Purpose Delays represent one of the most critical factors that affect the cost of a construction project. They have to be therefore analysed comprehensively using appropriate techniques. The purpose of this paper is to find out the delay analysis techniques (DATs) that are most commonly used in road projects in Sri Lanka, the extent of their usage, the criteria that can be used in selecting them and the technique that is most appropriate for the selection. Design/methodology/approach The research methodology adopted included an extensive literature review, expert interviews and a questionnaire survey. Findings In road projects in Sri Lanka, five types of DATs are mainly used. The “As-planned v. As-built Analysis” technique is the most commonly used technique while “Window Analysis” is the least used technique. Out of the nine criteria identified for selecting a DAT, the most important criterion is the acceptability of the technique to courts and tribunals. “Window Analysis” was found to be the most appropriate DAT that can be used in road construction projects in Sri Lanka. Originality/value “Window Analysis” can be recommended as the most appropriate DAT for road projects in Sri Lanka.

Item Type: Article
Uncontrolled Keywords: Sri Lanka; criteria; as-planned vs as-built analysis; delay analysis techniques; road construction; window analysis
Index terms: road project, construction project, window, methodology, research methodology, questionnaire, Sri Lanka, delay analysis, road construction, literature review, critical factor, survey, interview, tribunal
Subjects: data collection methods, risk assessment, research design and methodology, dispute resolution, data analysis and analytics, architectural elements, research methods, civil engineering, production management, Geography, infrastructure engineering, project controls
Topics: Time Control, Legal Issues, Design Practice, Risk Management, Research Practice, Geographical Context, Project Management, Engineering Principles
Descriptive scope: 5 PCTEA

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here