Vennström, A and Erik Eriksson, P (2010) Client perceived barriers to change of the construction process. Construction Innovation, 10(2), pp. 126-137. ISSN 1471-4175
Abstract
Purpose – The purpose of this paper is to identify clientperceived barriers to a change towards increased client influence on the end result of the construction process. Additionally, the variables of size of clients' markets and the extent of external project management are investigated in order to see how they influence the perceptions concerning important barriers to change. Design/methodology/approach – Empirical data were collected through a survey responded to by 87 Swedish construction clients. Findings – Identified barriers are divided into three types: attitudinal, industrial and institutional. Attitudinal barriers (adversarial attitudes, lack of ethics and morality, focus on projects instead of processes and a shortterm focus) and industrial barriers (traditional organization of the construction process, conservative industry culture, industry structure and traditional production processes) are perceived to be important, whereas institutional barriers (standard contracts, laws and traditional procurement procedures) are not perceived to be critical. Each different type of barrier is tested against the use of internal or external project management and the sphere of activity of the client. Attitudinal barriers are perceived as being more critical by clients using external project management. “Nearness” in terms of the sphere of activity (e.g. how large is the client's market?) also has an effect on how clients perceive the barriers. Locally, active clients do not consider attitudinal barriers to be as influential on the end result of the construction process as nationally active clients. Research limitations/implications – Since the empirical results are based on data collected only from Swedish clients, international generalizations should be made with caution. Practical implications – Clients wishing to act as change agents need to be aware that their use of internal versus external project management affects their chances to influence the other construction actors and implement change and innovation. Large national and international client organizations, which due to their size have significant opportunities to influence the industry, rely heavily on external project management, which may hamper their change agent role. Hence, such clients should make careful and purposeful selections of project management companies. Another more influential alternative is to strengthen their organisation and rely less on external project management. Originality/value – This paper presents a unique investigation of the connections between the use of internal/external project management and perceived barriers to change.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | change management; construction industry; construction operations; customer satisfaction; project management; Sweden |
| Index terms: | agent, construction process, methodology, change management, production process, survey, client organization, markets, construction industry, project management, investigation, morality, customer satisfaction, ethics, construction client, traditional procurement, Sweden, construction operation |
| Subjects: | industry analysis, building construction, Geography, service delivery, project management theory and practice, management, manufacturing engineering, research methods, construction operations, contractual arrangements, ethical practice, economic analysis, practitioner, data collection methods, client relations |
| Topics: | Engineering Principles, Geographical Context, Project Management, Research Practice, Business Strategy, Procurement, Roles and Professions, Stakeholder Management, Site Management, Organizational Design |
| Descriptive scope: | 5 PCTEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here