Poirier, E; Staub-French, S and Forgues, D (2015) Embedded contexts of innovation: BIM adoption and implementation for a specialty contracting SME. Construction Innovation, 15(1), pp. 42-65. ISSN 1471-4175
Abstract
Purpose - The purpose of this paper is to study the radical innovation process behind the adoption and implementation of building information modelling (BIM) for a specialty contracting small or medium enterprise (SME). This paper offers two distinct perspectives on BIM adoption and implementation, which are underrepresented in the current literature: the SME perspective and the specialty contractor perspective. It also attempts to bridge the gap between the growing literature on BIM adoption and implementation and the established literature on innovation by developing the notion of embedded contexts in the innovation process. Design/methodology/approach - A mixed-method, longitudinal case study approach was used in this research project to study the evolution of the innovation process and its impact on the Organisation over time. The objectives of this research were to investigate and document the different factors mediating the BIM adoption and implementation process for the Organisation across various contexts, the mechanisms put in place to facilitate this process and the perceived impact within the Organisation. Findings - The initial transition to BIM represented a radical innovation for the Organisation. Subsequently, a series of incremental innovations took place to further advance the Organisation’s BIM capabilities. This innovation process is influenced by different layers of embedded contextual factors, which can be mitigated by, among others, a clear strategic approach towards the innovation process. Furthermore, despite a limited sphere of influence, specialty contractors can leverage BIM within their own supply chain to reap significant benefits. Originality/value - This paper offers an in-depth study of radical innovation within a specialty contracting SME. This study discusses the influence of four embedded contexts on innovation for a specialty contracting SME: the industry context, the institutional context, the organisational context and the project context. It also offers insight into the factors, mechanisms and their impact on the innovation process.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | innovation,context,building information modelling,case study research,small or medium enterprise,specialty contractor |
| Index terms: | evolution, methodology, implementation, building information modelling, case study, specialty contractor |
| Subjects: | professional practice, environmental science, contractual arrangements, data collection methods, information systems, research methods |
| Topics: | Research Practice, Engineering Principles, Procurement, Sustainability, Digital Applications |
| Descriptive scope: | 4 PCTE |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here