Modelling standard cost commitment curves for contractors' cash flow forecasting

Kaka, A P and Price, A D F (1993) Modelling standard cost commitment curves for contractors' cash flow forecasting. Construction Management and Economics, 11(4), pp. 271-283. ISSN 01446193

Abstract

Cash flow forecasting and control are essential to the survival of any contractor. The time available for a detailed pre-tender cash flow forecast is often limited. Therefore, contractors require simpler and quicker techniques which would enable them to forecast cash flow with reasonable accuracy. This paper identifies causes behind the inaccuracy of current standard value S-curves (which are often used as an alternative approach for cash flow forecasting) and proposes the use of standard cost commitment models. The process of developing and testing the cost commitment models involved first collecting actual data for 150 completed projects. Several criteria were identified to classify these projects. Tests were conducted to identify which of these criteria affected the shape of the cost commitment curves. Projects were then distributed into different groups and S-curves were fitted into each using the logit transformation technique. Errors incurred when fitting these curves were measured and compared with those associates in fitting individual projects. Results showed that the difference between these errors was not significant. The reliability of selecting the cost commitment curve to model (instead of value curves) was evaluated. Results confirmed the hypothesis that cost commitment models are more accurate and reliable than value models. Finally, the paper outlines some of the practices involved in utilizing the proposed models.

Item Type: Article
Uncontrolled Keywords: anova tests; cash flow forecasting; cost commitment; cost control; s-curves
Index terms: cash flow forecasting, modelling, s-curve, cost control, testing, commitment, transformation, survival, cash flow, accuracy
Subjects: professional development, financial management, psychology, business, analytical methods, economics, financial and cost management, environmental science, professional practice
Topics: Business Strategy, Cost Management, Engineering Principles, Organizational Design, Sustainability, Information Management
Descriptive scope: 2 PC

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here