Chau, K W (1995) The validity of the triangular distribution assumption in Monte Carlo simulation of construction costs: Empirical evidence from Hong Kong. Construction Management and Economics, 13(1), pp. 15-21. ISSN 01446193
Abstract
This paper investigates the validity of the triangular distribution assumption which is commonly adopted in Monte Carlo sirnulations of construction costs. The study begins with an examination of the asymmetric nature of the distribution of construction costs and deduces theoretically that the triangular distribution assumption leads to an upward bias in the probability of exceeding the conventional single figure estimate for the subsystem variables and therefore the system variable. This assumption is also inconsistent with the estimators' subjective perception. An experiment has been performed to generate empirical data that test the above theoretical arguments and assesses the magnitude of the bias, if it indeed exists. Subjective estimates of the construction costs of the ten major subsystems of electrical services contracts of government clinics in Hong Kong are examined. These estimates are extracted from seven experienced estimators. The results of the analysis of the data confirm that the underlying distribution of the subsystem costs is asymmetric with a long thin tail towards the right and that the triangular distribution assumption does in fact lead to bias in the subsystem input variables and therefore the simulated output system costs. An alternative modelling approach which can reduce the bias has also been outlined in this paper.
| Item Type: | Article |
|---|---|
| Uncontrolled Keywords: | Monte Carlo simulation; probability density function; risk analysis; subjective estimates; triangular distribution |
| Index terms: | experiment, evidence, estimator, bias, risk analysis, Hong Kong, density, validity, construction cost, Monte Carlo simulation, modelling, estimate |
| Subjects: | probability and distributions, Geography, environmental hazards, evaluation and assessment methods, data collection methods, profession, modelling and simulation, financial and cost management, analytical methods |
| Topics: | Roles and Professions, Sustainability, Cost Management, Engineering Principles, Research Practice, Geographical Context, Urban Studies |
| Descriptive scope: | 4 PCEA |
N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here