Case-based allocation of onsite supervisory manpower for construction projects

Chen, J H; Yang, L R; Chen, W H and Chang, C K (2008) Case-based allocation of onsite supervisory manpower for construction projects. Construction Management and Economics, 26(8), pp. 805-814. ISSN 01446193

Abstract

In the highly competitive worldwide construction industry, a slight inaccuracy of estimation can easily cause the loss of a project. Erroneous experience-based cost estimates or allocations of onsite supervisory manpower often offset the profit gained from the project and may even jeopardize the management processes. To counter these types of problems, we develop a model using mathematical analysis and case-based reasoning to automate the allocation of onsite supervisory manpower and its costs. The method is founded upon laborious data collection processes and analysis by matching statistical assumptions, and is applicable to construction projects for residential buildings, industrial office buildings, commercial buildings and industrial construction. In the modelling the costs and allocation of onsite supervisory manpower are quantified for both owners and contractors before initiating or bidding on the projects. The findings confirm that the degree of variation of the model predictions has an accuracy rate at 88.47%. Single-site construction projects with the following characteristics: a non-crashing schedule, a floor area of less than 35 000 m2, a height of less than 50m, can be accurately predicted and the assignment of supervisory manpower feasibly automated.

Item Type: Article
Uncontrolled Keywords: allocation; human resource management; onsite; overheads; supervisory manpower costs
Index terms: mathematical analysis, bidding, commercial building, variation, construction project, human resource management, crashing, accuracy, profit, case-based reasoning, construction industry, cost estimate, modelling, industrial construction, overheads, owner, estimation, office building, onsite, residential building
Subjects: industry analysis, financial analysis, project controls, sociology, cognitive psychology, building construction, contractual condition, production management, professional development, management, data analysis and analytics, bidding, economic analysis, financial and cost management, analytical methods, construction type
Topics: Human Resources, Time Control, Contract Administration, Business Strategy, Cost Management, Project Management, Research Practice, Information Management, Engineering Principles, Stakeholder Management, Procurement, Construction Technology
Descriptive scope: 3 PCT

N.B. Descriptive scope is a count of how many of the five facets of empirical research are indicated by the words used in title, abstract and keywords. It is not intended as a judgement on the research; merely a count of the kind of word we would expect to indicate Phenomenon, Concepts, Theoretical framing, Empirical techniques, Analytical techniques. If all five are present, then a code of “5 PCTEA” will indicate this. If you feel the coding for this record is questionable, we welcome discussion around the terms we matched or the way we categorized them. The facet you would expect may not be coded, or a facet may be coded inappropriately. This can also bear on a larger question, of which facets should be treated as defining in construction management research. Please get in touch, and we will look at it. More details here